Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Fee triggers on
incomplete or uncorrected work
Also triggers if
plans/card unavailable on site
Unpaid fee means
no further inspections
Applies to
unincorporated areas only

Summary

Unincorporated Alameda County can bill a reinspection fee whenever an inspector shows up and the job isn't ready or the required corrections weren't made.

City-specific rules exist: Oakland, Livermore, Fremont, San Leandro, Berkeley, and Hayward have their own building inspections rules that differ from Alameda County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

A reinspection fee may be assessed, based on the established fee schedule, when inspection is called for but is not complete or when corrections called for are not made.

This Section 110.7 is not to be interpreted as requiring reinspection fees the first time a job is rejected for failure to comply with the requirements of this code, but as controlling the practice of calling for inspections before the job is ready for such inspection or reinspection.

Reinspection fees may be assessed when the inspection record card is not posted or otherwise available on the work site, the approved plans are not readily available to the inspector, there is failure to provide access on the date for which inspection is requested, or there is deviation from plans requiring the approval of the building official.

In instances where reinspection fees have been assessed, no additional inspection of the work will be performed until the required fees have been paid.

(Ord. No. 2025-72, Exh. B, 12-16-25)

Full Breakdown

The county's building code lets the building official accept inspection reports from approved outside agencies, including the director of public works on site-permit work. But the real teeth are in the reinspection rule: if work called for inspection isn't complete, or corrections ordered on an earlier visit weren't done, the county can charge a reinspection fee off its adopted fee schedule. That fee also applies if the inspection card isn't posted on site, approved plans aren't available for the inspector, the site isn't accessible on the scheduled date, or the work deviates from approved plans. Once a reinspection fee is assessed, the county won't send an inspector back out until it's paid, the first rejection on a job doesn't trigger the fee by itself.

Violations & Fines

Calling for an inspection before the job is ready, or not correcting flagged deficiencies, triggers a reinspection fee under AC §15.08.100; unpaid fees halt further inspections and can stall final approval.

Frequently Asked Questions

Will I be charged for a first failed inspection?
No: the code says the first time a job is rejected for noncompliance doesn't itself trigger a reinspection fee; the fee targets calling for inspections before you're ready.
What happens if I don't pay a reinspection fee?
No additional inspections are performed on the job until the required fees are paid, per AC §15.08.100.

Sources & Official References

Other rules in Alameda County

All Alameda County rules

California rules heatmap·Compare Alameda County to another location·View the California building safety overview

Get notified when Building Inspections in Alameda County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Cities Across Alameda County