Benton County, OR Building Safety: Building Inspections (2026)
Key Facts
- Governing section
- Benton County Code § 11.145
- Duty holder
- permit holder or authorized agent
- Required
- inspection record card posted on site
- Site status
- must stay accessible until inspected
- Re-inspection authority
- § 11.080, anytime
- Noncompliance remedy
- stop-work order, § 11.060
Summary
Under Benton County Code § 11.145, it's the permit holder, not the county, who must request every required inspection, keep the job site accessible, and post an inspection record card so the building official can log each visit. Work can't proceed past an inspection point until the building official signs off, and the card has to stay available on site until final approval closes out the permit.
11.145 - Inspections.(1)It shall be the duty of the permit holder or authorized agent to request all inspections that may be necessary or otherwise required in a timely manner, provide access to the site, and to provide all equipment as may be deemed necessary or appropriate by the building official. The permit holder shall not proceed with construction activity until authorized to do so by the building official. It shall be the duty of the permit holder to cause the work to remain accessible and exposed for inspection purposes. Any expense incurred by the permit holder to remove or replace any material required for proper inspection shall be the responsibility of the permit holder or his agent.(2)Work requiring a permit shall not be commenced until the permit holder or an agent of the permit holder has posted, or otherwise made available, an inspection record card such as to allow the building official to conveniently make the required entries thereon regarding inspection of the work. This card shall be maintained available by the permit holder until final approval has been granted by the building official.
Full Breakdown
145 puts the inspection burden squarely on the person doing the work. ' The permit holder can't move construction forward until the building official authorizes the next step, must keep the work 'accessible and exposed for inspection purposes,' and pays out of pocket if material has to be removed or replaced so the building official can actually see and inspect it. Subsection (2) adds the paperwork half of the duty: no permitted work can begin until the permit holder posts, or otherwise makes available, an inspection record card the building official can use to log each inspection, and that card has to stay available on site until the building official grants final approval.
080 lets the official re-inspect a completed building or structure at any time to confirm it's still being maintained in a safe and sanitary condition. 055 gives the building official a right of entry to inspect whenever there's reasonable cause to believe a building or premises violates the code or is unsafe, though entry into an occupied building requires presenting credentials and requesting entry first, or a warrant if entry is refused. 060 authorizes a written stop-work order until the building official specifically authorizes work to resume.
Violations & Fines
Failing to request required inspections, blocking site access, or covering up work before it's inspected violates § 11.145 and can bring construction to a halt: the building official can issue a written stop-work order under § 11.060 that stays in effect until the official specifically authorizes work to resume, and any material concealed before inspection may have to be removed or exposed again at the permit holder's own expense.
Frequently Asked Questions
Who is responsible for scheduling building inspections in Benton County?
What is the inspection record card and do I need to keep it on site?
Can Benton County re-inspect a building after construction is finished?
Sources & Official References
Other rules in Benton County
Compare Benton County to another location·View the Oregon building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.