Key Facts

First inspection
Foundation, due within 6 months of permit
Follow-up window
Each next inspection within 6 months of last pass
Missed deadline
Permit deemed invalid, must reapply
Enforcing office
Building Official, Codes and Building Services
General penalty
Up to $500 fine, 60 days jail (LDC § 1-5)
Right of entry
Building Official may enter on reasonable cause

Summary

Unincorporated Lee County's own amendment to the Florida Building Code sets a hard pace for every building permit: the foundation inspection is the "first inspection," and it must be finished within six months of the permit's issue date. Every inspection after that has to happen within six months of the last one that passed, or the Building Official can void the permit outright.

City-specific rules exist: Fort Myers has its own building inspections rules that differ from Lee County's county-level regulations. If you live in Fort Myers, check the city-specific page instead.

Foundation inspections. The first inspection required by the permit must be successfully completed within a six-month period of issuance or the permit will be deemed invalid. All subsequent inspections must be made within a six-month period of the most recent passed inspection until completion of work, or the permit will become invalid. For the purposes of this section, the foundation inspection will be considered the first inspection. The entire foundation must be completed within the first six months from the date of issuance of the permit. Partial inspections due to complexity of foundation may be made with building inspector's plans and job site plans and will be initialed by the inspector only on that portion of the plans that is inspected and these inspections are for compliance to plans and specifications and are in no way to be construed as the first inspection. Subsequent inspections may be made until the entire foundation is completed. At that time, the foundation will be signed off as the first inspection.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 7 | Land Development Code: Supplement 3 Update 3).

Full Breakdown

Lee County Land Development Code § 6-111 supplements Florida Building Code Chapter 1, Administration, with local amendments enforced by the Building Official in the Division of Codes and Building Services. 4 sets an inspection pace requirement that does not exist in the base state code: the foundation inspection is deemed the "first inspection" on any building permit, and it must be completed in full within six months of the date the permit issued. From there, every later inspection, framing, mechanical, electrical, plumbing rough-in, whichever trade comes next, must occur within six months of the last inspection that passed.

If that six-month window lapses at any point, the permit is deemed invalid and work must stop until a new permit is obtained and paid for again. Because complex foundations sometimes require staged pours, the code allows partial inspections against the inspector's plans and job-site plans along the way; those partial sign-offs confirm compliance with the approved plans but are not, by themselves, the "first inspection" that starts the clock. The foundation inspection is not complete, and the six-month clock does not start running, until the entire foundation has been inspected and signed off.

The same section amends FBC § 104 to give the Building Official right of entry to inspect any building, structure or premises whenever there is reasonable cause to believe a code violation makes it unsafe, dangerous or hazardous, and it authorizes the Building Official to suspend or revoke a permit that was issued in error, based on incomplete or inaccurate information, or where the actual construction departs from what the plans show. A permit is transferable to a new owner, but only after the Building Official receives actual notice of the transfer.

Violations & Fines

Letting a permit lapse under the six-month inspection rule costs more than time: Lee County Land Development Code § 1-5 makes any Code violation, including building without a valid permit after it lapses, punishable by up to a $500.00 fine, up to 60 days in the County Jail, or both, with each continuing day a separate offense. The Building Official can also suspend or revoke a permit for inaccurate applications or work departing from approved plans, and the Board of County Commissioners may seek an injunction to halt noncompliant construction.

Frequently Asked Questions

What counts as the "first inspection" on a Lee County building permit?
The foundation inspection is the first inspection under LDC § 6-111. It has to be completed in full within six months of the date your permit was issued. Partial inspections during a staged foundation pour document compliance with the plans but do not start or satisfy the six-month clock; only the completed, signed-off foundation does that.
What happens if I go more than six months between inspections?
Section 6-111 says any inspection more than six months after the last one that passed makes the permit invalid. That means construction has to stop, and you have to apply for and pay for a new building permit to resume work, even if the project was already well underway when the deadline slipped past.
Can a Lee County building inspector enter my property without permission?
Yes. Section 6-111 amends FBC § 104 to give the Building Official right of entry whenever there is reasonable cause to believe a building, structure or premises is unsafe or violates the Code. If the property is occupied, the Building Official must show credentials and request entry first; if entry is refused, the Building Official can seek an inspection warrant.

Sources & Official References

Other rules in Lee County

All Lee County rules

Florida rules heatmap·Compare Lee County to another location·View the Florida building safety overview

Get notified when Building Inspections in Lee County, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Cities Across Lee County