Fort Myers, FL Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

No-start lapse
180 days after issuance, no work
Inactivity lapse
180 days after last passing inspection
Missed-deadline result
Stop-work order, utility disconnection possible
Reinstatement
Written request, possible on-site inspection
Jurisdiction
City of Fort Myers, Lee County

Summary

In Fort Myers, Lee County, a building permit expires 180 days after issuance if work hasn't started, or 180 days after the last passing inspection, triggering stop-work orders and utility disconnection if not renewed.

(a)A building permit shall expire:(1)180 days after that date of issuance if work has not commenced; or(2)180 days after the last recorded passing inspection activity; or(3)As otherwise defined by the adopted building code.(b)Failure to renew or close a permit prior to the expiration date shall constitute a violation of this ordinance and may result in the following:(1)A stop work order, where applicable...(3)Disconnection of utilities.(4)Initiation to code enforcement for further action.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 60).

Full Breakdown

Fort Myers ties a building permit's validity directly to inspection activity. Under the Land Development Code, a permit expires 180 days after issuance if work has not commenced, or 180 days after the last recorded passing inspection: whichever milestone governs, or as otherwise set by the adopted building code. Missing that window is a code violation: the building official can issue a stop-work order, withhold future permit approvals for the property, disconnect utilities, and refer the matter to code enforcement. Reinstating an expired permit requires a written request with the permit number, a status of work completed, and an explanation of the delay, and the building official may order an on-site inspection to verify completed work before reactivating it.

Violations & Fines

Missing the inspection-driven 180-day window can bring a stop-work order, withheld future permit approvals, utility disconnection, and referral to code enforcement until the expired permit is resolved.

Frequently Asked Questions

How long is a Fort Myers building permit valid without a passing inspection?
It expires 180 days after issuance if work hasn't started, or 180 days after the last recorded passing inspection, under Land Development Code § 102-86.
What happens if my Fort Myers building permit expires?
The building official can issue a stop-work order, withhold future permit approvals, disconnect utilities, and refer the property to code enforcement until it's resolved.
Can an expired Fort Myers permit be reinstated?
Yes: submit a written request with the permit number, completed work status, and reason for delay; the building official may require an on-site inspection before reactivating it.

Sources & Official References

Other rules in Fort Myers

All Fort Myers rules

Florida rules heatmap·Compare Fort Myers to another location·View the Florida building safety overview

Get notified when Building Inspections in Fort Myers, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.