Fort Myers, FL Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit required for
buildings, signs, all construction
Issued by
building official or fire official
Permit expires
180 days if work not started
Enforcement tools
stop-work order, code enforcement referral
Governing section
Fort Myers Code § 102-81, § 102-86

Summary

Fort Myers requires a building permit from the building official or fire official before any construction, development, sign installation, or other work begins within city limits, unless specifically exempted by law.

No development or other construction may be undertaken or commenced within the city without a permit first being issued by the building official or fire official, as applicable, including buildings, signs or other construction, unless specifically exempted by law or regulation. The building official shall not issue any permit, except in conformity with the provisions of the land development code and other applicable city regulations and state statutes and all other laws and regulations.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 60).

Full Breakdown

Sec. 102-81 of the Fort Myers Code of Ordinances bars any development or construction, buildings, signs, or other work, from starting inside city limits without a permit issued by the building official or fire official, and the building official cannot issue one except in conformity with the Land Development Code and other applicable city, state, and federal requirements. Applications are reviewed against the growth management code and adopted building and fire codes, with construction drawings generally required at a scale of at least one-eighth inch per foot. Under Sec. 102-86, an issued permit expires 180 days after issuance if work hasn't commenced, or 180 days after the last passed inspection, whichever applies.

Violations & Fines

Working without a required permit, or letting one lapse past the 180-day window, can trigger a stop-work order, denial of future permit approvals for the property, utility disconnection, and referral to code enforcement under Sec. 102-86.

Frequently Asked Questions

Does Fort Myers require a permit before construction starts?
Yes. Sec. 102-81 bars any development or construction, including signs, from starting inside city limits without a permit from the building official or fire official, unless specifically exempted by law.
How long is a Fort Myers building permit valid before it expires?
It expires 180 days after issuance if work hasn't commenced, or 180 days after the last recorded passing inspection, per Sec. 102-86.

Sources & Official References

Other rules in Fort Myers

All Fort Myers rules

Florida rules heatmap·Compare Fort Myers to another location·View the Florida building safety overview

Get notified when Building Permits in Fort Myers, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Lee County handle building permits.

Cape Coral, FL
Some Restrictions