Fort Myers, FL Building Safety: Building Permits (2026)
Key Facts
- Permit required for
- buildings, signs, all construction
- Issued by
- building official or fire official
- Permit expires
- 180 days if work not started
- Enforcement tools
- stop-work order, code enforcement referral
- Governing section
- Fort Myers Code § 102-81, § 102-86
Summary
Fort Myers requires a building permit from the building official or fire official before any construction, development, sign installation, or other work begins within city limits, unless specifically exempted by law.
No development or other construction may be undertaken or commenced within the city without a permit first being issued by the building official or fire official, as applicable, including buildings, signs or other construction, unless specifically exempted by law or regulation. The building official shall not issue any permit, except in conformity with the provisions of the land development code and other applicable city regulations and state statutes and all other laws and regulations.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 60).
Full Breakdown
Sec. 102-81 of the Fort Myers Code of Ordinances bars any development or construction, buildings, signs, or other work, from starting inside city limits without a permit issued by the building official or fire official, and the building official cannot issue one except in conformity with the Land Development Code and other applicable city, state, and federal requirements. Applications are reviewed against the growth management code and adopted building and fire codes, with construction drawings generally required at a scale of at least one-eighth inch per foot. Under Sec. 102-86, an issued permit expires 180 days after issuance if work hasn't commenced, or 180 days after the last passed inspection, whichever applies.
Violations & Fines
Working without a required permit, or letting one lapse past the 180-day window, can trigger a stop-work order, denial of future permit approvals for the property, utility disconnection, and referral to code enforcement under Sec. 102-86.
Frequently Asked Questions
Does Fort Myers require a permit before construction starts?
How long is a Fort Myers building permit valid before it expires?
Sources & Official References
Other rules in Fort Myers
Florida rules heatmap·Compare Fort Myers to another location·View the Florida building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Permits in Nearby Cities
How other cities in Lee County handle building permits.