Key Facts

Enforcing agency
Planning and Community Development Director
Trigger
New construction, additions, occupancy changes
Required before occupancy
Final inspection finding no code violations
Code adopted
2021 International Building Code, locally amended
Permit expiration
365 days if work not started

Summary

Port Townsend requires the building official to inspect every new building, addition, or occupancy change and confirm no code violations before issuing a certificate of occupancy.

After the building official inspects the new building, structure, or addition, or any building or structure where the use or occupancy has changed, and finds no violations of the provisions of the codes adopted by Chapter 16.04 PTMC or other pertinent laws that are enforced by the jurisdiction, the building official shall issue a certificate of occupancy on a form developed by the City...

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 3364, passed May 18, 2026).

Full Breakdown

The city adopts the 2021 International Building Code's Chapter 1 administrative provisions (PTMC 16.04.040) to govern permitting and inspections for all construction. PTMC 16.04.070(A) amends IBC Section 111.2: the building official must inspect the completed building, addition, or occupancy change and find no violations of the adopted construction codes before a certificate of occupancy can issue. The director of planning and community development serves as building official (PTMC 16.04.050). Permits lapse if work isn't commenced within 365 days (PTMC 16.04.070(C)), so inspections must track an active permit timeline.

Violations & Fines

Occupying a building before the final inspection and certificate of occupancy issue violates PTMC 16.04; enforcement follows Chapter 1.20 PTMC, including civil penalties, criminal misdemeanor charges, and abatement orders.

Frequently Asked Questions

Who inspects new buildings in Port Townsend?
The director of planning and community development, acting as building official under PTMC 16.04.050, inspects the work.
When does Port Townsend issue a certificate of occupancy?
Only after the building official inspects the completed structure and finds no violations of the adopted codes, per PTMC 16.04.070(A).
What if required inspections aren't completed?
The city can withhold the certificate of occupancy and pursue civil or criminal enforcement under PTMC 1.20 and 16.04.100.

Sources & Official References

Other rules in Port Townsend

All Port Townsend rules

Compare Port Townsend to another location·View the Washington building safety overview

Get notified when Building Inspections in Port Townsend, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.