Sampson County, NC Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Enforcing official
Building Inspector
Rule
Sec. 2-18-04, Certificate of Occupancy
State authority
G.S. 160D-403(g)
Option
Temporary Certificate of Occupancy available
Revocation power
Sec. 2-18-11, Inspections Department

Summary

In unincorporated Sampson County, no new, altered, or moved building may be occupied until the Building Inspector issues a Certificate of Occupancy under Code Sec. 2-18-04, adopted pursuant to G.S. 160D-403(g). A Temporary Certificate of Occupancy can let part of a building be used safely before the whole project is finished.

These county ordinances apply to unincorporated areas of Sampson County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Pursuant to G.S. 160D-403(g), no new building or part thereof shall be occupied, and no addition or enlargement of any existing building shall be occupied, and no existing building after being moved shall be occupied, and no change of occupancy shall be made in any existing building or part thereof, until the Building Inspector has issued a Certificate of Occupancy therefore. A Temporary Certificate of Occupancy may, however, be issued by the Building Inspector for a building or portion of a building which may safely be occupied prior to final completion and occupancy of the entire building or for other temporary uses.

Full Breakdown

Sampson County Code Sec. 2-18-04, enacted under the 2025 Revised Zoning Ordinance effective February 21, 2025, bars occupancy of any new building, any addition or enlargement of an existing building, any building after it has been moved, or any building that changes use, until the Building Inspector issues a Certificate of Occupancy. The rule is adopted pursuant to G.S. 160D-403(g) and applies countywide in the unincorporated area, working alongside the Zoning Officer's broader enforcement duties set out in Sec. 2-18-02, which give the Zoning Officer authority to enter premises for inspection and to require Zoning Permits before construction begins.

Where a project is not fully finished but part of it can safely be used, the Building Inspector may issue a Temporary Certificate of Occupancy so that portion, or another temporary use, can proceed while remaining work continues. Enforcement reaches beyond the certificate itself: Sec. 2-18-11 lets the Zoning Officer, acting through the Sampson County Inspections Department, revoke a building or occupancy permit under G.S. 160D-403(f) whenever the method of construction or the use of the building violates the ordinance, meaning an occupancy certificate already issued is not the end of the county's oversight if a violation later comes to light.

Together these sections make the Building Inspector, not the property owner or contractor, the final checkpoint before any building in unincorporated Sampson County can lawfully be used or its use changed.

Violations & Fines

Occupying or changing the use of a building before the Building Inspector issues a Certificate of Occupancy is a violation of Sec. 2-18-04 and Sec. 2-18-06, exposing the owner to the penalties in Sec. 2-18-09 under G.S. 160D-404 and G.S. 153A-123, with each day of continued unauthorized occupancy treated as a separate violation. The Sampson County Inspections Department can also revoke an already-issued permit under Sec. 2-18-11 if construction method or use violates the ordinance.

Frequently Asked Questions

Can I move into a new building in Sampson County before an inspection?
No. Sec. 2-18-04 of the Sampson County Code requires the Building Inspector to issue a Certificate of Occupancy before any new, enlarged, moved, or use-changed building may be occupied, so occupancy before that inspection and certificate is a violation of the ordinance.
Is there a way to use part of a building before it's fully finished?
Yes. Sec. 2-18-04 lets the Building Inspector issue a Temporary Certificate of Occupancy for a building, or a portion of one, that can safely be used before the entire project reaches final completion, or for other qualifying temporary uses recognized under the same section.
Can Sampson County revoke an occupancy permit after it's issued?
Yes. Sec. 2-18-11 authorizes the Zoning Officer, acting through the Sampson County Inspections Department, to revoke a building or occupancy permit under G.S. 160D-403(f) if the method of construction or the actual use of the building violates the zoning ordinance.

Sources & Official References

Other rules in Sampson County

All Sampson County rules

Compare Sampson County to another location·View the North Carolina building safety overview

Get notified when Building Inspections in Sampson County, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.