Key Facts

Footing inspection
before any concrete is poured
Final inspection
required before occupancy
Failure-to-request fee
$250 per instance
Reinspection fee
$200 per hour

Summary

Sioux Falls building permits move through staged inspections, starting with a footing inspection before any concrete is poured and ending with final sign-offs from the electrical, mechanical, plumbing and building divisions before occupancy.

R109.1.1 Footing inspection. Inspection of the footing shall be made after poles or piers are set or trenches or basement areas are excavated and any required forms erected and any required reinforcing steel is in place and supported prior to the placing of concrete. The footing inspection shall include excavations for thickened slabs intended for the support of bearing walls, partitions, structural supports, or equipment and special requirements for wood foundations.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-135: Current through local ordinance 54-26, passed 7-14-2026).

Full Breakdown

Under the city's amended International Residential Code, building services must inspect work at defined stages before it can be covered up or occupied. The footing inspection happens after forms and any required reinforcing steel are set, but before concrete is placed (R109.1.1). Homes in flood hazard areas also need a floodplain elevation inspection before further vertical construction (R109.1.3). No one- or two-family dwelling can be occupied, and no certificate of occupancy issued, until the electrical, mechanical, plumbing and building inspection divisions have each completed a final inspection and signed the placard on the electrical panel (R110.1).

Violations & Fines

Building without the required inspection risks a $250 administrative fee for failure to request a required inspection, plus a $200 reinspection fee, and blocks issuance of a certificate of occupancy until inspections are completed (Table 1-C; R110.1).

Frequently Asked Questions

When does the city inspect the footing?
After forms and any required reinforcing steel are in place, but before concrete is poured, per R109.1.1 of Sioux Falls' amended residential code.
Can a new home be occupied before final inspection?
No. R110.1 bars occupancy and a certificate of occupancy until the electrical, mechanical, plumbing and building divisions have all signed off with final inspections.

Sources & Official References

Other rules in Sioux Falls

All Sioux Falls rules

Compare Sioux Falls to another location·View the South Dakota building safety overview

Get notified when Building Inspections in Sioux Falls, SD changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.