Texas City, TX Building Safety: Building Inspections (2026)
Key Facts
- Morning inspection notice
- Due before 5:00 p.m. the preceding day
- Afternoon inspection notice
- Due before 12:00 noon the same day
- City inspection window
- 48 hours, exclusive of Sundays and holidays
- Reinspection fee, § 151.060(A)
- $1, on new written notice at least 24 hours later
- Reinspection fee schedule, § 151.053(C)
- $25 first, then $50, $100, $150
- Temporary connection
- Not exceeding 30 days, on written application
- Inspecting officer
- City Inspector
Summary
In Texas City, Texas, electrical work moves through written notice, inspection, reinspection and a final certificate of inspection issued by the City Inspector. Notice for a morning inspection is due before 5:00 p.m. the preceding day, and the city takes 48 hours, exclusive of Sundays and holidays, to inspect and report.
(B) Notice that the work is ready for inspection must be given at the office of the City Inspector, for morning inspections, before 5:00 p.m. the preceding day, and for afternoon inspections, before 12:00 noon the same day. A period of 48 hours, exclusive of Sundays and holidays, will be required in which to make inspection and report. ... (A) If, after the first visit to a job on written notice to inspect the job, it is necessary to return to reinspect, or it is necessary to reinspect any work, whether from a defect or the work not being ready, the Inspector will return only on another written notice and not less than 24 hours after the notice, and shall charge a fee of $1 for so doing, all other notices taking precedence. (B) After the entire completion of the work, a notice shall be given the Inspector for a final inspection; and, if he or she finds that the work has been satisfactorily done, he or she shall issue a final certificate of inspection on the request of the electrical contractor holding the permit, as provided in this chapter.
Full Breakdown
This page covers the electrical inspection stages in Chapter 151 of the Texas City Code of Ordinances, which apply to wiring inside the city limits, not to unincorporated Galveston County. The permit comes first: § 151.050 requires a written application to the Electrical Inspector with the plans, specifications and schedules needed to judge whether the installation conforms.
When the work is ready, § 151.057 requires written notice on blanks furnished at the City Inspector's office, stating the location of the work, the owner's name and the name of the electrician doing the work. Notice for a morning inspection is due before 5:00 p.m. the preceding day, and notice for an afternoon inspection is due before 12:00 noon the same day. Under § 151.058 the inspector then tells the electrician in charge when the inspection will happen and tests the work in the electrician's presence. On large and complicated jobs the inspector can approve inspecting and testing in sections.
Sequencing matters. Section 151.056 requires all plumbing and other piping or tube work on work to be concealed to be in place before the wiring is inspected. Section 151.061 makes it unlawful to lath, seal or otherwise conceal wiring or equipment until it has been inspected and the inspector has posted a notice at the service switch or another suitable place.
A return visit costs money. Under § 151.060(A) the inspector returns only on another written notice and not less than 24 hours after it, for a fee of $1. The fee schedule in § 151.053(C) prints a different figure: $25 for the first reinspection, then $50, $100, $150 and so on. The code prints both figures without reconciling them.
After the entire work is complete, a notice is given for a final inspection, and § 151.060(B) has the inspector issue a final certificate of inspection on the request of the electrical contractor holding the permit. Section 151.055(A) makes it unlawful to use current in the wiring until that certificate issues. On written application, § 151.062 lets the City Inspector give temporary permission to connect for a period not exceeding 30 days where there is an urgent necessity. The final certificate does not relieve the contractor of responsibility for defective work (§ 151.067).
Violations & Fines
Using electric current in wiring that has not been inspected and approved, with the final certificate issued, is unlawful under § 151.055(A), and hindering or interfering with the City Inspector is unlawful under § 151.066. Both carry a penalty reference to § 10.99: a fine not exceeding $500, or $2,000 where the case arises under the fire safety, zoning or public health ordinances, with each day a separate offense. Unsafe conductors must be fixed within 24 hours or the time the inspector sets, or the service wires can be disconnected under § 151.059.
Frequently Asked Questions
When must I give notice to get an electrical inspection in Texas City?
What does a reinspection cost in Texas City?
Can power be connected before the final certificate is issued?
Can a homeowner do their own wiring in Texas City?
Sources & Official References
Other rules in Texas City
Texas rules heatmap·Compare Texas City to another location·View the Texas building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.