Building stages
Foundation, frame, final (§ 5-37(8)(f))
Between stages
Written release required
Before occupancy
Certificate of occupancy needed
Concealing before release
Violation (§ 5-37(8)(g))
Enforcing official
Building inspector

Summary

Whitfield County Code § 5-37(8)(f) sets three required building inspections for permitted work: a foundation inspection after trenches are excavated and forms erected, a frame inspection once framing and rough systems are in place, and a final inspection before occupancy. Work cannot proceed past each stage without the building inspector's written release.

These county ordinances apply to unincorporated areas of Whitfield County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

f.Required inspections. The building inspector upon notification from the permit holder or his agent shall make the following inspections and such other inspections as necessary, and shall either release that portion of the construction or shall notify the permit holder or his agent of any violations which must be corrected in order to comply with the technical code: Building. 1.Foundation inspection. To be made after trenches are excavated and forms erected.2.Frame inspection. To be made after the roof, all framing, fireblocking and bracing are in place, all concealing wiring, all pipes, chimneys, ducts and vents are complete.3.Final inspection. To be made after the building is completed and ready for occupancy.

Full Breakdown

Section 5-37(8)(f) lays out the required inspections by trade, in order. For building work, the foundation inspection happens after trenches are excavated and forms erected; the frame inspection happens after the roof, all framing, fireblocking and bracing are in place and all concealed wiring, pipes, chimneys, ducts and vents are complete; and the final inspection happens after the building is completed and ready for occupancy. Parallel stage inspections apply to the other trades in the same section: electrical work gets an underground inspection, a rough-in inspection, and a final inspection; plumbing gets underground, rough-in, and final inspections, with rough-in covering the point after the roof and framing are in place and all soil, waste and vent piping is complete; and mechanical and gas systems follow their own underground/rough-in/final and rough-piping/final-piping/final sequences.

Under § 5-37(8)(g), work cannot proceed past the point covered by each inspection without first getting a written release from the building inspector, and reinforcing steel, structural framing, insulation, and plumbing, mechanical or electrical systems cannot be covered or concealed without that release either. A certificate of occupancy under § 5-37(9)(a) is not issued until all required electrical, gas, mechanical, plumbing and fire protection systems have passed inspection and been released by the building inspector.

Violations & Fines

Covering or concealing work, such as framing, insulation, or piping, before the building inspector releases that stage violates § 5-37(8)(g) and can require the covering to be opened back up for inspection. Occupying a building before the certificate of occupancy issues under § 5-37(9)(a) is itself a code violation, and the general misdemeanor penalty in § 5-4 applies: up to a $1,000.00 fine, up to 60 days in jail, or both, with each day a separate offense.

Frequently Asked Questions

When does the foundation inspection happen?
After the trenches for the foundation are excavated and the forms are erected, per § 5-37(8)(f). The building inspector checks this stage before any concrete work proceeds further.
Can I close up my walls before the frame inspection?
No. Section 5-37(8)(g) requires a written release from the building inspector before work proceeds past the point covered by each required inspection, and the frame inspection specifically covers the roof, framing, fireblocking, bracing, and concealed wiring, pipes, chimneys, ducts and vents while they're still visible.
When can I move into a new home in unincorporated Whitfield County?
Not until the building inspector issues a certificate of occupancy under § 5-37(9)(a), which requires the final building, electrical, gas, plumbing and mechanical inspections to pass first. Occupying the structure before that certificate issues is a code violation.

Sources & Official References

Other rules in Whitfield County

All Whitfield County rules

Compare Whitfield County to another location·View the Georgia building safety overview

Get notified when Building Inspections in Whitfield County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.