Data Centers & Crypto Mining in Camarillo, CA (2026)
2 verified data centers & crypto mining rules for Camarillo, California, sourced directly from the municipal code and official government pages.
Verified from official government sources
Data Center Zoning & Siting
The City of Camarillo has no data-center ordinance and no "data center" use category. A data center is sited in the M-1 Light Manufacturing or M-2 General Manufacturing zone, classified as manufacturing, office, or public-utility use, and requires a discretionary development plan or planned development permit with CEQA review.
Camarillo Data Center Zoning and Siting
Few RestrictionsCamarillo, CA, Municipal Code Sec. 19.30.030 (M-1 Light Manufacturing Zone - Uses permitted)
No building or improvements may be erected, constructed, converted, established, altered or enlarged, nor may a lot or premises be used until a development plan has been submitted to, and approved by, the planning commission unless otherwise set forth in this code.
Data Center Noise Limits
Camarillo's noise ordinance, Chapter 10.34, caps sound at the receptor property line using the ambient level plus an increment. Base exterior limits are 65 dBA day and 55 dBA night on industrial land, and 55/45 dBA at homes, with a hard 45 dBA residential cap overnight.
Camarillo Data Center Noise Limits
Some RestrictionsCamarillo, CA, Municipal Code Sec. 10.34.040(C) (Exterior noise standards)
With respect to residential receptor properties, the exterior noise level may not exceed forty-five dBA between the hours of nine p.m. and seven a.m.
Looking for Ventura County county-wide rules?
County ordinances apply to unincorporated areas and may supplement Camarillo city rules.
Data Centers & Crypto Mining in Ventura County →