Data Centers & Crypto Mining in Galt, CA (2026)
2 verified data centers & crypto mining rules for Galt, California, sourced directly from the municipal code and official government pages.
Verified from official government sources
Data Center Zoning & Siting
The City of Galt has no data-center ordinance and no "data center" use category. Data centers locate in the two industrial zones - LM (Light Industrial) and M (Industrial) - permitted by right as research, development, or warehousing, or by Minor Use Permit if classed as a telecommunications facility.
Galt Data Center Zoning and Siting
Few RestrictionsGalt, CA, Municipal Code § 18.32.020 (Purpose of Industrial Zoning Districts); Table 18.32-1 (§ 18.32.040)
The M zoning district is intended to accommodate a broad range of manufacturing and industrial uses. Permitted activity may vary from medium to higher intensity uses that involve the manufacture, fabrication, assembly, or processing of raw and/or finished materials.
Data Center Noise Limits
The City of Galt caps exterior noise at the affected property: 50 dB(A) daytime and 45 dB(A) nighttime hourly Leq, with maximum levels of 70 and 65 dB. Municipal Code § 8.40.040 sets the standard; a data center's cooling and generators must comply at the nearest home.
Galt Data Center Noise Limits
Some RestrictionsGalt, CA, Municipal Code § 8.40.040 (Exterior Noise Standards)
It is unlawful except as otherwise specified in this chapter for any person at any location within the City to create any noise which causes the noise levels on an affected property, when measured in the designated noise area, to exceed for the duration of time set forth following, the specified exterior noise standards in any one (1) hour by:
Looking for Sacramento County county-wide rules?
County ordinances apply to unincorporated areas and may supplement Galt city rules.
Data Centers & Crypto Mining in Sacramento County →