Galt, CA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Few Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified July 2026

Key Facts

Dedicated ordinance
None
Zones
LM and M industrial
By-right
R&D, warehousing, utility
Minor Use Permit
Telecommunications facility
Discretionary review
CEQA + Planning

Summary

The City of Galt has no data-center ordinance and no "data center" use category. Data centers locate in the two industrial zones - LM (Light Industrial) and M (Industrial) - permitted by right as research, development, or warehousing, or by Minor Use Permit if classed as a telecommunications facility.

The M zoning district is intended to accommodate a broad range of manufacturing and industrial uses. Permitted activity may vary from medium to higher intensity uses that involve the manufacture, fabrication, assembly, or processing of raw and/or finished materials.

Source: Galt Municipal Code - Development Code Ch. 18.32 (Industrial Zoning) & Noise Control Standards Ch. 8.40View official code

Full Breakdown

Galt's Development Code (Municipal Code Title 18) does not name "data center" as a use. Chapter 18.32 creates two industrial zones - LM (Light Industrial) and M (Industrial) - and Table 18.32-1 lists permitted uses. A data center classified as Research and Development, Wholesale and Distribution, or a Utility Substation is permitted by right, needing only a ministerial building permit. Classified as a Telecommunications Facility, it requires a Minor Use Permit. Higher-intensity manufacturing needs a Conditional Use Permit in the LM zone. Discretionary permits trigger CEQA review by the Planning Division. Galt has adopted no data-center ordinance and no moratorium.

Violations & Fines

Building or operating a data center outside the LM or M industrial zones, or without a Minor or Conditional Use Permit when required, is a Development Code violation enforced by Code Compliance through stop-work orders, penalties, and abatement.

Frequently Asked Questions

Where can data centers be built in the City of Galt?
In the two industrial zones - LM (Light Industrial) and M (Industrial) - under Development Code Chapter 18.32. There is no data-center use, so the Planning Division classifies each project into the closest listed use in Table 18.32-1.
Does Galt require a special permit for a data center?
Not always. Many are permitted by right as research and development or warehousing. One classified as a Telecommunications Facility needs a Minor Use Permit; higher-intensity manufacturing in the LM zone needs a Conditional Use Permit and CEQA review.
Does Galt have a data-center ordinance, and who decides?
No. Galt has no data-center ordinance or moratorium; industrial zoning and noise rules govern. Residents wanting tailored standards can advocate to the Planning Commission or City Council via the Planning Division: https://www.cityofgalt.org/government/community-development/planning

Sources & Official References

Other rules in Galt

All Galt rules

California rules heatmap·Compare Galt to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Galt, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Sacramento County handle data center zoning & siting.

Citrus Heights, CA
Some Restrictions
Sacramento, CA
Few Restrictions
Rancho Cordova, CA
Few Restrictions
Folsom, CA
Significant Restrictions
Elk Grove, CA
Significant Restrictions