Data Centers & Crypto Mining in Idaho Falls, ID (2026)

1 verified data centers & crypto mining rules for Idaho Falls, Idaho, sourced directly from the municipal code and official government pages.

Verified from official government sources

Crypto Mining Rules

Idaho Falls Power charges server farms and crypto mining operations a High Density Load Rate once energy use intensity hits 250 kWh per square foot yearly, capping peak load at 1,000 kW per customer and site.

Idaho Falls Crypto Mining Power Rate

Some Restrictions

Idaho Falls City Code Section 8-5-24(D)

(D) HIGH DENSITY LOAD RATE: This rate shall be applicable at a single point of delivery and one location per customer, for all energy requirements delivered to server farms, crypto currency, data processing or similar technological operations with an energy use intensity (EUI) of 250kWh/ft²/year or more and with peak electrical load up to one thousand kilowatts (1,000 kW). Customers shall not c...

Looking for Bonneville County county-wide rules?

County ordinances apply to unincorporated areas and may supplement Idaho Falls city rules.

Data Centers & Crypto Mining in Bonneville County