Idaho Falls, ID Data Centers & Crypto Mining: Crypto Mining Rules (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

EUI threshold
250 kWh/ft2 per year
Peak load cap
1,000 kW per customer/site
Covers
server farms, crypto mining, data centers
Rate set by
City Council resolution
Utility
Idaho Falls Power (municipal)

Summary

Idaho Falls Power charges server farms and crypto mining operations a High Density Load Rate once energy use intensity hits 250 kWh per square foot yearly, capping peak load at 1,000 kW per customer and site.

(D) HIGH DENSITY LOAD RATE: This rate shall be applicable at a single point of delivery and one location per customer, for all energy requirements delivered to server farms, crypto currency, data processing or similar technological operations with an energy use intensity (EUI) of 250kWh/ft²/year or more and with peak electrical load up to one thousand kilowatts (1,000 kW). Customers shall not create separate entities or other means to circumvent the maximum of one thousand kilowatts (1,000 kW) per customer and location within the City.

Full Breakdown

Idaho Falls Power, the city-owned utility, bills server farms, crypto-currency mining, data processing, and similar tech operations under a High Density Load Rate once energy use intensity reaches 250 kWh per square foot per year. Peak electrical load is capped at 1,000 kW per customer and location, and the Code expressly forbids splitting a mining operation into separate accounts or entities to duck the cap. Rate components (energy, demand, credit-risk deposit, distribution connection fee) are set by Council resolution, not fixed in the Code text.

Violations & Fines

There's no criminal penalty tied to this section: it's a billing rule. Operations that hit the 250 kWh/ft2/year threshold are simply moved onto the High Density Load Rate, and attempts to dodge the 1,000 kW cap through separate entities are disregarded and billed as one customer.

Frequently Asked Questions

Does Idaho Falls ban crypto mining operations?
No outright ban. Idaho Falls Power instead bills mining and data-processing operations under a High Density Load Rate once their energy use intensity reaches 250 kWh/ft2/year, capped at 1,000 kW peak load per customer and location.
Can a miner split into multiple accounts to avoid the rate?
No. City Code Section 8-5-24(D) explicitly bars creating separate entities or other means to circumvent the 1,000 kW cap per customer and location within the City.

Sources & Official References

Other rules in Idaho Falls

All Idaho Falls rules

Compare Idaho Falls to another location·View the Idaho data centers & crypto mining overview

Get notified when Crypto Mining Rules in Idaho Falls, ID changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.