Environmental Rules in Meriden, CT (2026)
4 verified environmental rules for Meriden, Connecticut, sourced directly from the municipal code and official government pages.
Verified from official government sources
Stormwater Management
Meriden's sewer ordinance requires stormwater and other unpolluted drainage to go only into pipes designated as storm sewers, never into the sanitary sewer system. Section 170-9 of Chapter 170 bars anyone from discharging groundwater, roof runoff or subsurface drainage into a sanitary sewer, and bars connecting a drain or plumbing fixture on private property to a stormwater sewer.
Meriden Stormwater Discharge To Storm Sewers
Some RestrictionsMeriden Code § 170-9
§ 170-9. Stormwater and unpolluted drainage. Stormwater and all other unpolluted drainage shall be discharged to such sewers as are specifically designated as storm sewers in accordance with all applicable state and federal laws and regulations. No person shall discharge or cause to be discharged any unpolluted waters, such as stormwater, groundwater, roof runoff, and subsurface drainage, to an...
Erosion Control
Any Meriden development disturbing more than half an acre must file a certified soil erosion and sediment control plan under Section 213-57, and grading is barred on slopes of 20 percent or steeper unless it is part of an approved plan. Single-family homes outside a subdivision are exempt, and noncompliance draws an immediate cease and desist order.
Meriden Soil Erosion and Sediment Control
Some RestrictionsMeriden Code § 213-57
A soil erosion and sediment control plan shall be submitted with any application for development when the disturbed area of such development is cumulatively more than 1/2 acre. ... No development, grading of the land or stripping of vegetation shall be permitted on slopes of 20% or steeper ... unless part of an approved development, excavation or filling plan with an erosion and sediment contro...
Flood Zones
In the City of Meriden, a development permit must be obtained before any construction or development begins within an area of special flood hazard, administered by the City Engineer under Chapter 110.
Meriden Floodplain Development Permit
Some RestrictionsMeriden Code § 110-12
A development permit shall be obtained before construction or development begins within any area of special flood hazard established in § 110-7. Application for a development permit shall be made on forms furnished by the administrator and may include, but not be limited to, plans in duplicate drawn to scale showing the nature, location, dimensions, and elevations of the area in question; exist...
Flood Elevation Requirements
In the City of Meriden, new and substantially improved residential structures in areas of special flood hazard must have their lowest floor, including basement, elevated to or above the base flood elevation plus one foot of freeboard.
Meriden Freeboard: BFE Plus One Foot
Some RestrictionsMeriden Code § 110-19
Residential construction: New construction and substantial improvement of any residential structure shall have the lowest floor, including basement, elevated to or above base flood elevation, plus one foot. ... Nonresidential construction: New construction and substantial improvement of any commercial, industrial or other nonresidential structure shall either have the lowest floor, including ba...