Environmental Rules in Pueblo, CO (2026)
4 verified environmental rules for Pueblo, Colorado, sourced directly from the municipal code and official government pages.
Verified from official government sources
Stormwater Management
Pueblo requires developers of sites disturbing an acre or more to build permanent stormwater quality best management practices under the City's Stormwater Utility Ordinance.
Pueblo Stormwater BMP Rule for New Development
Some RestrictionsPueblo Municipal Code § 16-12-10(a)
Applicable development sites must incorporate permanent stormwater quality best management practices. These requirements shall apply unless the City approves and documents an allowable exclusion according to policy adopted by the Director of the stormwater utility enterprise having been approved by City Council. Each developer of real property within the City shall provide all necessary stormwa...
Erosion Control
Pueblo requires owners and operators of construction sites disturbing an acre or more to run erosion and sediment control BMPs through final site stabilization.
Pueblo Construction Erosion Control Rule
Some RestrictionsPueblo Municipal Code § 16-12-10(b)
Owner or operator of applicable construction activity must implement adequate construction stormwater best management practices (BMPs) to control erosion, sediment-laden runoff and waste from the site. These requirements shall apply unless the City approves and documents an allowable exclusion according to policy adopted by the Director of the stormwater utility enterprise having been approved ...
Flood Zones
Pueblo requires a Floodplain Development Permit for any construction in FEMA-mapped Special Flood Hazard Areas within city limits.
Pueblo Floodplain Development Permit
Some RestrictionsPueblo Municipal Code § 17-9-3
This Chapter shall apply to all Special Flood Hazard Areas and areas removed from the floodplain by the issuance of a FEMA Letter of Map Revision Based on Fill (LOMR-F) within the jurisdiction of the City of Pueblo, Colorado.(b)Basis for establishing the Special Flood Hazard Area. The Special Flood Hazard Areas identified by the Federal Emergency Management Agency in a scientific and engineerin...
Flood Elevation Requirements
Pueblo requires new and substantially improved buildings in flood zones to sit at least 1 foot above base flood elevation.
Pueblo Base Flood Elevation Freeboard
Some RestrictionsPueblo Municipal Code § 17-9-5(b)(1)
Residential construction. New construction and Substantial Improvement of any residential structure shall have the lowest floor (including basement), elevated to one (1) foot above the base flood elevation. Upon completion of the structure, the elevation of the lowest floor, including basement, shall be certified by a registered Colorado Professional Engineer, architect or land surveyor. Such c...