Data Center Zoning & Siting
Roseville has no dedicated data-center ordinance. Under Title 19 a data center is classified as a Specialized Industrial use, requiring a Conditional Use Permit in the MP, M1, and M2 industrial zones and permitted by right only in the MMU zone.
Roseville Data Center Zoning and Siting
Significant RestrictionsRoseville, CA, Municipal Code Sec. 19.14.010(B) (Light Industrial (M1) District); Sec. 19.14.020 (Industrial Zone Districts Permitted Uses - Specialized Industrial requires CUP in MP/M1/M2)
Light Industrial (M1) District. The light industrial district is intended to designate areas appropriate for light industrial uses such as manufacturing, processing, assembly, high technology, research and development and storage uses.
Data Center Noise Limits
Roseville caps fixed-source noise at a sensitive receptor's property line at 50 dBA daytime (7 a.m.-10 p.m.) and 45 dBA at night, per Municipal Code Chapter 9.24. Industrial sources abutting homes get a 7 dBA allowance; data-center cooling and generators must comply.
Roseville Data Center Noise Limits
Some RestrictionsRoseville, CA, Municipal Code Sec. 9.24.100 (Sound limits for sensitive receptors) & Table 1; Sec. 9.24.120 (Sound limits for industrial properties)
It is unlawful for any person at any location to create any sound... which causes the exterior sound level when measured at the property line of any affected sensitive receptor to exceed the ambient sound level by three dBA or exceed the sound level standards as set forth in Table 1, by three dBA, whichever is greater.