Los Angeles, CA Data Centers & Crypto Mining: Data Center Moratoriums (2026)

Few Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified July 2026

Key Facts

Moratorium
None adopted
Pending action
Council File 26-0262
Introduced
February 24, 2026
Committee
Pending in PLUM
Data centers
Still allowed

Summary

The City of Los Angeles has not adopted a data-center moratorium, cap, or ban. Instead, Council File 26-0262 (February 24, 2026) directs City Planning to draft a definition and zoning framework, and asks LADWP to assess grid, water, and climate impacts.

I THEREFORE MOVE that the City Council instruct the Department of City Planning, to report back with recommended amendments... to: 1. Create a clear and comprehensive definition of 'Data Center'... and 2. Establish appropriate use classifications and zoning permissions for Data Centers, including identification of the zones in which such uses are permitted by right, permitted conditionally, or prohibited.

Source: City of Los Angeles — Council File 26-0262 (Data Centers / Zoning Code) & LAMC Ch. XI Noise RegulationView official code

Full Breakdown

There is no data-center moratorium in the City of Los Angeles. On February 24, 2026, Councilwoman Monica Rodriguez introduced Council File 26-0262, 'Data Centers / Zoning Code. Definition and Regulatory Framework,' which was referred to the Planning and Land Use Management (PLUM) Committee. The motion instructs the Department of City Planning to report back with amendments creating a data-center definition, assigning use classifications, and identifying where the use is permitted by-right, conditionally, or prohibited, plus additional safeguards. It also asks LADWP to assess impacts on the power grid, water resources, and climate goals. The file remains pending in committee and no ordinance or moratorium has been adopted.

Violations & Fines

With no moratorium, there is nothing to violate on that basis. Data centers must still meet industrial zoning, obtain building and electrical permits, complete CEQA when discretionary, and comply with the City noise ordinance.

Frequently Asked Questions

Is there a data center moratorium in the City of Los Angeles?
No. The City has not adopted a moratorium, cap, or ban. Council File 26-0262 (February 2026) proposes a definition and zoning framework, but it is still pending in committee.
What would Council File 26-0262 do?
It directs City Planning to create a data-center definition, set zoning permissions, and recommend safeguards, and asks LADWP to assess grid, water, and climate impacts. It is a framework step, not a ban.

Sources & Official References

Other rules in Los Angeles

All Los Angeles rules

California rules heatmap·Compare Los Angeles to another location·View the California data centers & crypto mining overview

Get notified when Data Center Moratoriums in Los Angeles, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.