Acworth, GA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permitted district
Heavy Industrial (HI) only
Approval type
Special Use, Mayor and Board of Aldermen
Use table section
§ 73-4.4
HI district list
§ 73-5.11(D)(3), item 3
All other districts
Not permitted (dash in Use Table)

Summary

Acworth's Use Table permits crypto mining operations, server farms, and data centers in exactly one zoning district, Heavy Industrial (HI), and even there only as a Special Use requiring Mayor and Board of Aldermen approval. Every residential, commercial, office, and Light Industrial column in the table shows the use as flatly not permitted.

INDUSTRIAL R-1 R-2 R-3 R-5 RM-6 RM-8 C-1 C-2 OP L1 HI ... crypto mining, server farms, data centers — — — — — — — — — — S ... D.Special Uses Permitted by Board of Aldermen.1. ... Adult Entertainment.2.Extended Stay Facilities.3. ... Cryptocurrency mining operations, server farms, and/or data centers.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 27).

Full Breakdown

4, the Zoning Ordinance's Use Table, lists "crypto mining, server farms, data centers" under the Industrial use category with a dash in every column except one: the Heavy Industrial (HI) district, marked "S" for Special Use. 3 fire and heat standards, unless the Board expressly modifies them as part of the special-use approval. 11(D)(3) confirms the same limitation from the district side: the HI district's list of "Special Uses Permitted by Board of Aldermen" names "Cryptocurrency mining operations, server farms, and/or data centers" third, alongside adult entertainment, extended stay facilities, recycling collection centers, and telecommunications towers.

11(A) as intended for major manufacturing, warehousing, and research facilities requiring open storage and large amounts of land, uses that may affect the surrounding environment, with access to major streets and utilities. No other district in the table, including Light Industrial (L1), C-1, C-2, OP, or any residential district, carries an entry for this use, so a data center or mining operation cannot locate anywhere else in the city regardless of the applicant's willingness to meet the supplemental fire, heat, and noise standards.

Violations & Fines

Operating a data center, server farm, or crypto mining facility outside the Heavy Industrial district, or without the required Special Use permit inside it, is an unpermitted use under Section 73-10.2: the Development Director can order the use to cease, withhold a certificate of occupancy, or revoke any permit issued, and the operator faces civil penalties up to $1,000.00 per day and criminal fines up to $1,000.00 or 60 days in jail under Section 73-10.2.4, with each day a separate offense.

Frequently Asked Questions

Can a data center locate in Acworth's Light Industrial district?
No. The Section 73-4.4 Use Table shows a dash, meaning not permitted, in every district column for crypto mining operations, server farms, and data centers except Heavy Industrial. Light Industrial, C-1, C-2, OP, and all residential districts are excluded.
What approval does a data center need in the Heavy Industrial district?
A Special Use permit from the Mayor and Board of Aldermen under Sections 73-4.3(B)(4) and 73-5.11(D)(3). It is not a by-right use even in HI, and the Board can attach or modify conditions as part of approval.
Does the Special Use permit replace the fire and heat rules?
No. Section 73-4.3(B)(4) keeps a Special Use subject to all other Zoning Ordinance requirements, including the Section 73-7.4.3 fire suppression, containment, and heat standards, unless the Board expressly modifies them when it grants the permit.

Sources & Official References

Other rules in Acworth

All Acworth rules

Compare Acworth to another location·View the Georgia data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Acworth, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.