Skip to main content
CityRuleLookup

Apple Valley, MN Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Where a data center is listed
Zone 2 of the Ordinance No. 1053 designation, § A37-2(B)(3)
Status in Zone 2
Permitted use, no conditional use permit named
Zone 2 minimum lot
40,000 square feet, 200 feet wide
Zone 2 building height
45 feet maximum
Zone 2 building coverage
30 percent of the lot
Zone 1 status
Data center not listed; limited to home improvement uses

Summary

In the City of Apple Valley, Minnesota, the only place the Code of Ordinances names a data center as a use is Zone 2 of the property designated by Ordinance No. 1053, where it is a permitted use. Zone 2 carries 40,000 square foot lots, 45 foot height and 30 percent building coverage.

(B) Zone 2. Within this this zone, no structure or land shall be used except for one or more of the following uses deemed similar by the City Council: (1) Conducting a process, fabrication, storage, manufacturing or wholesaling operation; (2) Contractor's office, outdoor storage subject to a conditional use; (3) Data center; (4) On-sale wine, and/or 3.2% liquor in conjunction with an event center/banquet facility; (5) Health and fitness club, when located in a freestanding building; (6) Manufacturing related to aerospace, medical device, and pharmaceutical industries; (7) Medical reference and diagnostic laboratories; (8) Offices;

Full Breakdown

Article A37 of the Apple Valley Code of Ordinances, adopted by the City Council as Ordinance No. 1053 on 11-15-18, sets performance standards for one mapped planned development in Dakota County, Minnesota. Section A37-1 states the purpose of the zone: an integrated mix of retail and general business, and limited industrial uses. The designation is split into Zone 1 and Zone 2. Zone 1 is limited to a building materials and home improvement store and a garden sales center, so a data center cannot go there.

Zone 2 is where section A37-2(B) lists "Data center" as item (3) among its permitted uses, next to process and fabrication operations, offices, laboratories, warehousing and wholesale businesses, and manufacturing related to aerospace, medical device and pharmaceutical industries. The lead-in language says no structure or land in Zone 2 is used except for the listed uses or uses deemed similar by the City Council. Section A37-3(B) adds a separate conditional use list for Zone 2: fleet vehicle operations storage and maintenance, on-sale liquor, outdoor research or testing facilities, outdoor storage of vehicles and materials in conjunction with a permitted use, and towers as regulated in § 155.385.

Section A37-5 then fixes the dimensional standards for Zone 2: minimum lot area of 40,000 square feet, lot width of 200 feet, building setbacks of 50 feet along principal or arterial streets, 40 feet along collector streets, 30 feet along all other streets, 25 feet along private streets or drives measured from the back of the curb, 10 feet on the side lot line and 20 feet on the rear lot line. Maximum building coverage is 30 percent of the lot and maximum building height is 45 feet.

Impervious surface, screening, landscaping and parking cross-refer to §§ 155.350, 155.348, 155.349 and 155.370 through 155.379. Section A37-6 requires refuse and recycling equipment to be fully screened from public streets and adjacent properties. The Code contains no other data center provision, so a data center anywhere else in the city needs the zoning ordinance itself to allow it or a rezoning through the City Council.

Violations & Fines

The Zone 2 provisions quoted here print no penalty of their own. A use outside the A37-2(B) permitted list and not deemed similar by the City Council is not allowed in Zone 2, and a use on the A37-3(B) list requires a conditional use. Dimensional limits in section A37-5 bind every improvement placed on the land.

Frequently Asked Questions

Is a data center allowed anywhere in Apple Valley, Minnesota?
The Apple Valley Code of Ordinances names a data center in one place only: section A37-2(B)(3), which lists it as a permitted use in Zone 2 of the property designated by Ordinance No. 1053. No other district in the Code lists the use by name, so any other site depends on the City Council approving a use deemed similar or a rezoning.
Does a Zone 2 data center need a conditional use permit?
Not for the data center itself. Section A37-2(B) puts it on the permitted list. Section A37-3(B) is the separate conditional use list for Zone 2, and it covers fleet vehicle operations, on-sale liquor, outdoor research or testing facilities, outdoor storage of vehicles and materials in conjunction with a permitted use, and towers under § 155.385.
What setbacks and height apply in Zone 2?
Section A37-5 sets Zone 2 building setbacks at 50 feet along principal or arterial streets, 40 feet along collector streets, 30 feet along all other streets, 25 feet along private streets or drives, 10 feet on the side lot line and 20 feet on the rear lot line. Building height tops out at 45 feet and coverage at 30 percent.
Can a data center go in Zone 1 of the same designation?
No. Section A37-2(A) limits Zone 1 to a building materials supply and home improvement store and a garden sales center, plus uses deemed similar by the City Council under the lead-in wording. A data center appears only in the Zone 2 list under section A37-2(B).

Sources & Official References

Other rules in Apple Valley

All Apple Valley rules

Compare Apple Valley to another location·View the Minnesota data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Apple Valley, MN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.