Solano County, CA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified July 2026

Key Facts

Dedicated Ordinance
None; general industrial zoning
Zones
M-L, M-G-1/2, M-G-3, I-WD
M-L Setbacks
30 ft front / 10 ft side
Review Trigger
Sec. 28.95 + CEQA
Jurisdiction
Unincorporated county only

Summary

Solano County has no dedicated data center ordinance. In the unincorporated county, a data center is treated as an industrial use and belongs in the M-L, M-G, or I-WD manufacturing districts under Chapter 28. Large facilities trigger performance-standards review and CEQA. Cities set their own zoning.

City-specific rules exist: Vallejo has its own data center zoning & siting rules that differ from Solano County's county-level regulations. If you live in Vallejo, check the city-specific page instead.

The purpose of the M-G District is to permit the normal operations of almost all industries, subject only to those regulations needed to control congestion and to protect the surrounding area or adjoining premises.

Source: Solano County Code, Chapter 28 (Zoning Regulations)View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 1868, passed April 9, 2026).

Full Breakdown

Unincorporated Solano County regulates data centers only through its general industrial zoning, not a data-center-specific chapter. Under Chapter 28, computing and server facilities fit the Manufacturing-Limited (M-L) 'industrial park' district (research, warehousing, electronics manufacturing) or the Manufacturing-General (M-G-1/2, M-G-3) districts, where 'general manufacturing' is allowed by right. Because a large data center carries utility-scale power and cooling, the Zoning Administrator can invoke the Section 28.95 performance-standards procedure, and any use permit or discretionary approval triggers CEQA review. M-L setbacks are 30-foot front, 10-foot side, 50-foot height; M-G is 10-foot front and 20-foot side. No data centers currently operate in the unincorporated county. This applies only to unincorporated land; the seven cities each apply their own zoning.

Violations & Fines

Building a data center on land not zoned M-L, M-G, or I-WD, or ignoring performance-standards conditions or required CEQA review, is a zoning violation. Solano County can withhold building permits, issue stop-work orders, and pursue code enforcement.

Frequently Asked Questions

Where can a data center be built in unincorporated Solano County?
In the M-L, M-G, or I-WD manufacturing districts under Chapter 28. There is no data-center-specific rule, so the county classifies it as an industrial use, and large facilities require performance-standards review and CEQA.
Does Solano County zoning apply inside its cities?
No. Chapter 28 governs only unincorporated Solano County. Fairfield, Vacaville, Vallejo, Benicia, Dixon, Rio Vista, and Suisun City each adopt and enforce their own zoning codes within city limits.
Does Solano County have data center rules, and how can I weigh in?
No, Solano County has no dedicated data-center ordinance. To advocate for one, contact the Solano County Board of Supervisors: https://www.solanocounty.gov/government/board-supervisors

Sources & Official References

Other rules in Solano County

All Solano County rules

California rules heatmap·Compare Solano County to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Solano County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Cities Across Solano County