Key Facts

Setback from rivers/schools/residential
750 feet minimum
Setback from commercial property
100 feet minimum
Vegetated buffer (residential-adjacent)
200 feet wide
Security fence
8 ft, anti-climb, no barbed wire
Noise limit at boundary
55 dB(A), 52 dB(A) tonal
Open space outside urban services area
40% minimum

Summary

Stafford County's Zoning Ordinance sets data-center-specific standards: 750-foot setbacks from the Rappahannock and Potomac Rivers, schools and residential property, a 200-foot vegetated buffer, 8-foot anti-climb security fencing, and noise capped at 55 dB(A) at the site boundary, under Section 28-39(q).

These county ordinances apply to unincorporated areas of Stafford County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(1)Setback standards.a.All primary structures shall be set back at least seven hundred fifty (750) feet from any property line abutting the Rappahannock River or Potomac River, an existing or approved school that will be owned or operated by Stafford County School Board, or a school as defined in this chapter, or from any property line abutting or across public right-of-way from a residential use or undeveloped properties that are zoned for residential use, and at least one hundred (100) feet from any property line abutting or across public right-of-way from commercial zoned properties. ... a vegetated buffer shall be required consisting of a landscaped strip at least two-hundred (200) feet wide. ... The site shall be enclosed with security fencing at least eight (8) feet in height, include an appropriate anti-climbing device, and shall be secured with gates. ... The use of chain link or barbed wire fencing shall be prohibited, except for fences surrounding electrical substations.

Full Breakdown

Section 28-39(q) of the Zoning Ordinance adds a dedicated set of siting standards for data center development on top of the county's general zoning rules. Primary structures must sit back at least 750 feet from any property line abutting the Rappahannock or Potomac Rivers, an existing or approved Stafford County school, or a residential use or residentially zoned undeveloped property, and at least 100 feet from commercially zoned property. Accessory structures, parking, loading areas, outdoor storage and substation facilities must stay 300 feet from a school, residential use or residentially zoned land, and 300 feet from an assisted living facility, nursing home, park or child care center.

Sites abutting residential property need a vegetated buffer at least 200 feet wide, and outside the urban services area, at least 40 percent of the site must remain open space. Every data center must be enclosed with security fencing at least 8 feet high with an anti-climbing device and gates, and chain-link or barbed-wire fencing is prohibited except around electrical substations. Building-mounted lighting cannot exceed 30 feet in height, and site lighting is capped at 15 footcandles. m. The board of supervisors can modify these buffers and setbacks during a zoning reclassification based on a viewshed or noise study.

Violations & Fines

A data center built without meeting Section 28-39(q)'s setback, buffer, fencing, lighting or noise standards can be denied site plan approval, and post-development sound studies conducted for ten years after occupancy can trigger further enforcement if noise limits are exceeded. An unspecified violation defaults to a Class 1 misdemeanor under Section 1-11, up to a $2,500 fine, twelve months in jail, or both.

Frequently Asked Questions

How far must a data center be from homes in Stafford County?
At least 750 feet. Section 28-39(q) requires data center primary structures to set back 750 feet from any property line abutting a residential use, residentially zoned undeveloped land, a Stafford County school, or the Rappahannock or Potomac Rivers.
Can a data center use barbed wire fencing in Stafford County?
No, with one exception. Section 28-39(q) prohibits chain-link or barbed-wire fencing at data centers, except around electrical substations, and requires the rest of the site to be enclosed with at least 8-foot security fencing with an anti-climbing device.
What noise limit applies to a Stafford County data center?
Facility noise is capped at 55 dB(A) measured at the property boundary under Section 28-39(q), dropping to 52 dB(A) where a discrete prominent tone is present, and the county requires pre- and post-development sound studies plus ten years of annual monitoring.

Sources & Official References

Other rules in Stafford County

All Stafford County rules

Compare Stafford County to another location·View the Virginia data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Stafford County, VA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.