Key Facts
- Governing section
- LCC § 17.142.102
- Facade rule
- No mirrored glass or polished metal
- Entrance rule
- Differentiated entrance, projects/recesses 5+ feet
- Lighting rule
- Must meet LCC § 17.142.020(3)(e)
- Enforcement
- Civil infraction/misdemeanor, Ch. 1.20 LCC
Summary
Lewis County requires a data processing center in unincorporated areas to be fully enclosed, faced with non-reflective materials and a differentiated main entrance, and lit to the same downward-shielded standard as every other land use, under LCC § 17.142.102.
Each violation of the provisions of this title or the provisions of any regulation, order, permit or ruling promulgated pursuant thereto shall constitute a civil infraction. Infractions shall be processed according to the provisions of Chapter 1.20 LCC and subject to the penalties of that chapter. In addition, any violation of the provisions of this title or the provisions of any regulation, order, permit or ruling promulgated pursuant thereto shall be a misdemeanor. Each violation shall constitute a separate offense for each and every day or portion thereof during which the violation is committed, continued, or permitted. ... (2) Building Facade. (a) Reflective surfaces, such as mirrored glass or polished metal, are prohibited. (b) The main entrance shall be differentiated from the building facade by a change in material, pattern, texture or color and the entrance shall project or recess from the adjoining building plane by at least five feet. (3) Lighting. All exterior lighting shall meet the standards of LCC § 17.142.020(3)(e), lighting.
Full Breakdown
020. The building facade rules in subsection (2) prohibit reflective surfaces such as mirrored glass or polished metal on a data center building, and require the main entrance to be visually differentiated from the rest of the facade through a change in material, pattern, texture or color; the entrance also has to project or recess at least five feet from the adjoining building plane. 020(3)(e), meaning fixtures must be pointed downward, hooded and shielded to prevent glare and trespass onto neighboring parcels. 102 functions as Lewis County's siting package for this use: a data center has to be designed, screened, faced and lit in a way that keeps its industrial character from spilling into rural and small-town character areas.
Violations & Fines
A data processing center that skips the facade or lighting standards can be denied or conditioned by Community Development during permit review, and a facility built out of compliance is treated the same as any other Title 17 violation: LCC § 17.07.010 makes it a civil infraction under Chapter 1.20 LCC and a misdemeanor, with each day of noncompliance a separate offense.
Frequently Asked Questions
Does Lewis County have zoning standards specific to data centers?
Can a data center building have reflective glass walls?
What lighting standard applies to a data center site?
Sources & Official References
Other rules in Lewis County
Compare Lewis County to another location·View the Washington data centers & crypto mining overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.