Key Facts

Zoning district
Advanced Manufacturing District only
Use classification
Permitted (by right), not conditional
Front setback
40 feet from right-of-way
Max height
60 feet, plus 10 for screened mechanicals
Max lot coverage
80 percent
Site plan review
Required under Chapter 1151 before permit

Summary

In the City of Oregon, Ohio, a data center is a use permitted by right only in the Advanced Manufacturing District. Codified Ordinances Section 1145.02 lists 'Data Center' with a 'Permitted' designation, and Section 1145.12 defines it as a facility that houses computer systems and is focused on the mass storage of data.

1145.02 PERMITTED, ACCESSORY AND CONDITIONAL USES. The following uses, as defined in Section 1145.12, shall be considered as permitted, accessory or conditional as denoted in the following table: Use Permitted Conditional Accessory ... Data Center X ... DATA CENTER - A facility that houses computer systems and associated data and is focused on the mass storage of data.

Full Breakdown

02's use table marks 'Data Center' with an 'X' in the Permitted column, the same column carrying Advanced Manufacturing, Logistics, Flex-Office and Research and Development uses. 12 defines a data center narrowly as a facility that houses computer systems and associated data and is focused on the mass storage of data, and that definition controls over any conflicting definition elsewhere in the Zoning Code. 04(a), a 25-foot side and rear setback that grows to 60 feet where the lot adjoins single-family zoning, an 80% maximum lot coverage, and a 60-foot maximum building height (with up to 10 additional feet for screened rooftop mechanical equipment).

05 requires brick, stone, precast concrete or similar masonry-type facades, limiting textured block to 20% of any wall. 11 requires Site Plan Review under Chapter 1151 before the Zoning Inspector issues a permit. 03 strictly prohibits any use not listed in the table, chemical plants, power plants, petroleum refineries and steel mills cannot locate on the same site as a permitted data center.

Violations & Fines

Building or operating a data center anywhere the Zoning Code does not list it as permitted, conditional or accessory, or without completing Site Plan Review under Section 1145.11, is a Zoning Ordinance violation. Section 1105.99 makes that a misdemeanor punishable by up to $100 per offense plus costs, with each day of noncompliance after notice charged as a separate offense against the owner, tenant, contractor or other responsible party.

Frequently Asked Questions

Is a data center allowed in Oregon, Ohio?
Yes, but only in the Advanced Manufacturing District. Section 1145.02 lists 'Data Center' as a permitted use there, and it is not listed as permitted, conditional or accessory in any other zoning district in the code.
What size and height limits apply to a data center building?
In the Advanced Manufacturing District, Section 1145.04 caps building height at 60 feet (plus up to 10 feet for screened rooftop mechanical equipment), limits lot coverage to 80%, and requires a 40-foot front setback and a 25-foot side and rear setback.
Does a data center need site plan approval before construction?
Yes. Section 1145.11 requires every development in the Advanced Manufacturing District, including a data center, to complete Site Plan Review under Chapter 1151 before the Zoning Inspector will issue a zoning permit for construction or a change of use.
Can a data center locate next to a chemical plant or refinery in Oregon, Ohio?
No. Section 1145.03 strictly prohibits chemical plants, power plants, petroleum refineries and steel mills anywhere in the Advanced Manufacturing District, so a permitted data center cannot share the district with those heavier industrial uses.

Sources & Official References

Other rules in Oregon

All Oregon rules

Compare Oregon to another location·View the Ohio data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Oregon, OH changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.