Key Facts

Scope
Applies only in unincorporated Flagler County
Permit authority
County building official issues the permit
Prerequisite
State and federal agency approval required first
Application
Scaled drawing (1 in = 100 ft) required
Waterway depth
Minimum 8 ft below mean low water
Default penalty
Up to $500 fine, up to 60 days jail

Summary

Before building a bulkhead, boat dock or pier on waterfront property in unincorporated Flagler County, the owner must get a construction permit from the county building official, and that approval only follows sign-off from the relevant state and federal agencies. The Land Development Code also sets minimum waterway depth and requires a scaled drawing showing the structure's exact location.

These county ordinances apply to unincorporated areas of Flagler County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

B.Bulkheads, Boat Docks, and Piers. Prior to the construction by the applicant of any bulkhead, boat dock or pier, a construction permit shall be obtained from the building official after approval by appropriate state and federal agencies. A drawing at a scale of one (1) inch = one hundred (100) feet, or such other scale approved by those agencies, showing the location of the bulkhead, boat dock or pier shall be presented at the time of permit application.

Full Breakdown

09 of the Land Development Code, governing waterfront developments, treats bulkheads, boat docks and piers as construction projects requiring their own permit track. S. Army Corps of Engineers for work below the mean high-water line, have signed off. The application package must include a drawing at a scale of one inch to one hundred feet, or another scale those agencies accept, pinpointing the bulkhead, dock or pier's location. The same section separately regulates dredging, filling and excavation along the waterfront: any dredge, fill or excavation permit likewise requires county commission approval of a plat before work begins, under subsection A.

Where the work involves constructing a new waterway, subsection C sets a minimum channel depth of eight feet below mean low water across a continuous twenty-foot bottom width, so the waterway can handle tidal and wind-driven water movement. These waterfront development standards apply only in unincorporated Flagler County; a dock built from a Palm Coast, Flagler Beach or Beverly Beach address falls under that city's own permitting process instead.

Violations & Fines

The Land Development Code does not set a stand-alone fine inside § 4.06.09; building without the required permit falls under the Code's general default penalty at § 1-6, punishable by a fine of up to $500, up to 60 days in the county jail, or both, with each day a continuing violation counted as a separate offense. The county can also revoke or suspend a permit and pursue civil penalties or injunctive relief.

Frequently Asked Questions

Do I need a permit to build a dock on my waterfront lot in unincorporated Flagler County?
Yes. LDC § 4.06.09.B requires a construction permit from the county building official before building any bulkhead, boat dock or pier, and that permit issues only after the appropriate state and federal agencies, typically the Florida DEP and the Army Corps of Engineers, approve the work first.
What has to be included with the permit application?
A drawing showing the exact location of the bulkhead, boat dock or pier, drawn at a scale of one inch to one hundred feet or another scale those state and federal agencies accept, must be submitted at the time of application under LDC § 4.06.09.B.
Does this rule apply to docks in Palm Coast or Flagler Beach?
No. This is a Flagler County Land Development Code standard that governs only the unincorporated area of the county. Palm Coast, Flagler Beach and Beverly Beach each administer their own waterfront construction permitting process under their own separate municipal codes, so check with that city instead.
What if I build a dock without the permit?
Building without the required LDC § 4.06.09.B permit falls under the county's general default penalty at § 1-6: a fine of up to $500, up to 60 days in jail, or both, with each day the violation continues counted as a separate offense, plus possible permit revocation.

Sources & Official References

Other rules in Flagler County

All Flagler County rules

Florida rules heatmap·Compare Flagler County to another location·View the Florida environmental rules overview

Get notified when Boat Dock Permits in Flagler County, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Boat Dock Permits in Cities Across Flagler County