Billings, MT Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Trigger
1 acre or within 50 ft of waterway
Required filings
NOI, SWPPP, and NOT forms
Inspection frequency
Every 14 days, self-documented
Enforcer
Public works department, environmental division
Penalty
Misdemeanor, up to $500/day

Summary

Construction disturbing 1+ acre, or within 50 feet of a watercourse, must file a Notice of Intent and Storm Water Pollution Prevention Plan with Billings before breaking ground, under the city's Chapter 28 stormwater rules.

The city will require at a minimum an executed copy of the state standard notice of intent (NOI) form for a storm water discharge associated with construction activity under the general permit and a storm water pollution prevention plan (SWPPP), and a notice of termination (NOT) for construction sites either one acre or larger, for each phase of a construction site that exceeds one acre, or within fifty (50) feet of any water course including irrigation and stormwater ditches for construction sites of less than one acre.

Source: Billings Public WorksView official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 66 Update 2).

Full Breakdown

Chapter 28 of the Billings Municipal Code implements the city's MS4 stormwater permit and incorporates Montana's construction stormwater general permit (ARM 17.30.1301, 17.30.601). Any project disturbing one acre or more, or working within 50 feet of a watercourse, including irrigation and stormwater ditches, even on sites under one acre, must submit a state Notice of Intent, keep a Storm Water Pollution Prevention Plan on site, and file a Notice of Termination when work ends. Permittees must self-inspect BMPs at least every 14 calendar days and within 10 days of major storm events, documenting each inspection for city review.

Violations & Fines

Skipping the NOI/SWPPP, failing to install or maintain erosion control devices, or letting sediment leave the site onto adjoining property or right-of-way are code violations, each a separate misdemeanor offense punishable by up to a $500 fine per day.

Frequently Asked Questions

Does Billings require an erosion control plan for construction?
Yes: sites disturbing 1 acre or more, or within 50 feet of a watercourse, must file an NOI and keep a SWPPP on site before starting work.
Who enforces stormwater and erosion rules on job sites?
The city's public works department/environmental division, which inspects active sites and can issue stop-work orders under Article 18-300.

Sources & Official References

Other rules in Billings

All Billings rules

Compare Billings to another location·View the Montana environmental rules overview

Get notified when Erosion Control in Billings, MT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.