Washington County, UT Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
Grading on slopes over 20% (§10-24-5)
Erosion duty during construction
Control water/runoff, no silt to storm drains (§10-24-6.F.16)
Financial guarantee
Bond required if disturbance exceeds 1 acre (§10-24-7)
Restoration deadline
1 year from permit issuance (§10-24-7)
Enforcement
Public works director can halt construction (§10-24-11)
Appeal window
10 calendar days to request commission hearing (§10-24-10)

Summary

Any grading or construction on slopes over 20% in unincorporated Washington County needs a hillside development permit, and the drainage plan submitted with it must control erosion and storm runoff throughout construction. The county public works director enforces the standard and can halt work for violations.

City-specific rules exist: St. George has its own erosion control rules that differ from Washington County's county-level regulations. If you live in St. George, check the city-specific page instead.

15. Necessary measures shall be taken to prevent erosion and scour at all points throughout the development. It shall be mitigated at all points of discharge and at the face of any cut or fill slope throughout the development.

16. During grading or construction on any property, including off site construction, the developer shall control both water used for construction and storm runoff in such a manner as to not adversely affect any adjoining properties, nor add silt or debris to any existing storm drain, wash, channel or roadway.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-17: Code current through: Ord. 2026-1329-O, passed 8-18-2026).

Full Breakdown

Washington County Code Title 10, Chapter 24 (Hillside Development Standards) requires a grading development permit for any development on slopes exceeding twenty percent (20%), granted by the county commission after review by county staff and the land use authority under section 10-24-5. The permit application must include a drainage control plan and report under section 10-24-6(F), which spells out erosion and sediment obligations for the construction phase itself, not just the finished grading: crews must prevent erosion and scour at every point of discharge and at the face of every cut or fill slope, and during grading or construction, including off-site work, the developer must control both construction water and storm runoff so adjoining properties are not affected and no silt or debris reaches any storm drain, wash, channel, or roadway.

The application must also include a drainage plan showing all surface and subsurface drainage systems, walls, cribbing, or other erosion protection devices, plus a geology and soils report addressing slope stability and erosion, and the drainage plans and construction drawings must be approved by the public works director before final plat or site approval and before any building permit issues. Under section 10-24-7, projects disturbing more than one acre (or smaller sites the public works director flags) must post a cash bond or irrevocable letter of credit before the permit issues, sized to cover soil stabilization, grading, planting, and maintenance; if restoration is not completed within one year, the county can call the bond and finish the work itself.

Retention and detention basins are barred outright on hillsides under 10-24-6(F)(12), and independent storm systems triggered by street-capacity overruns must be sized for a 10-year storm at minimum, with a 12-inch minimum storm drain. Chapter 24 exempts strictly mining or mineral-development grading under section 10-24-12 unless the public works director requires compliance anyway.

Violations & Fines

Under section 10-24-11, the public works director or building official may order an immediate halt to construction on any hillside development where a condition violates, or threatens to violate, Chapter 24, including its erosion and drainage requirements. The stop-work order stays in effect until the official is satisfied the developer has brought the site into substantial compliance, and this authority is in addition to the general penalties in subsections 10-1-21(A) and (B). A developer who disagrees with a staff requirement can request a county commission hearing under section 10-24-10 by submitting a written request within ten calendar days.

Frequently Asked Questions

Does Washington County require erosion control during hillside construction?
Yes. Section 10-24-6(F)(15)-(16) of the county code requires developers to prevent erosion and scour at every discharge point and cut or fill face, and to control construction water and storm runoff so silt and debris do not reach adjoining properties or any storm drain, wash, channel, or roadway while grading is underway.
What triggers the hillside grading permit in unincorporated Washington County?
Any development on a slope exceeding twenty percent (20%) needs a grading development permit under section 10-24-5, reviewed by county staff and the land use authority and granted by the county commission before any grading or construction activity starts.
What happens if a hillside project in Washington County violates the erosion rules?
The public works director or building official can order a halt to construction under section 10-24-11 whenever a condition violates or threatens to violate Chapter 24. Work stays stopped until the county is satisfied the site is in substantial compliance, on top of the penalties in section 10-1-21.
Is a bond required for erosion and hillside restoration work?
Yes, for any project disturbing more than one acre (and sometimes smaller sites), section 10-24-7 requires a cash bond or irrevocable letter of credit covering soil stabilization, grading, planting, and maintenance before the permit is issued, with a one-year deadline to finish restoration.

Sources & Official References

Other rules in Washington County

All Washington County rules

Compare Washington County to another location·View the Utah environmental rules overview

Get notified when Erosion Control in Washington County, UT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Washington County