Effingham County, GA Environmental Rules: Erosion Control (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit fee
$40.00 per acre or fraction
Performance bond
$1,500.00 per acre or fraction
State-waters buffer
25 feet (50 feet for trout streams)
Civil penalty ceiling
$2,500.00 per day, per violation
Permitting agency
Developmental services department

Summary

Land-disturbing activity in unincorporated Effingham County requires a permit and an approved best-management-practices erosion, sedimentation, and pollution control plan, a $40-per-acre fee, a $1,500-per-acre bond, and violations carry civil penalties up to $2,500 per day.

These county ordinances apply to unincorporated areas of Effingham County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Sec. 30-121. - General provisions. Excessive soil erosion and resulting sedimentation can take place during land-disturbing activities if requirements of the ordinance and the NPDES General Permit are not met. Therefore, plans for those land-disturbing activities which are not exempted by this article shall contain provisions for application of soil erosion, sedimentation and pollution control measures and practices. ... (c)A fee in the amount of $40.00 for each acre shall be charged for each acre or fraction thereof in the project area. ... (g)The permit applicant shall post a bond ... in the ... amount of $1,500.00 per acre or fraction thereof of the proposed land-disturbing activity, prior to issuance of the permit.

Full Breakdown

Effingham County Code § 30-121 requires that any land-disturbing activity not exempted under § 30-113 include a plan applying soil erosion, sedimentation, and pollution control measures conforming to the minimum requirements of §§ 30-122 and 30-123, covering street and utility installation, drainage facilities, and all temporary and permanent improvements, at every stage of the activity. Under § 30-132(a), no person may conduct land-disturbing activity in the unincorporated county without first obtaining a permit from the developmental services department, submitting five copies of the plan, and, per § 30-132(c), paying a fee of $40.00 for each acre or fraction thereof in the project area.

Section 30-132(g) also requires a bond of $1,500.00 per acre or fraction of the proposed activity before permit issuance, refundable once final stabilization is reached. Section 30-122 requires 25 to 50-foot vegetative buffers along state waters and trout streams under § 30-123(15) and (16), with no land-disturbing activity permitted inside an undisturbed buffer until the site achieves final stabilization. Enforcement under § 30-142 starts with a written warning for a first or second violation, giving five days to correct before a stop-work order issues; a third violation triggers an immediate stop-work order.

Section 30-144 sets civil penalties up to $2,500.00 per day for violating any provision, permit condition, or emergency order, with each day of continued violation a separate offense, enforceable in magistrate court or any court of competent jurisdiction.

Violations & Fines

Conducting land-disturbing activity without the required permit exposes a person to revocation of any business license under § 30-141, a written warning followed by a stop-work order under § 30-142, bond forfeiture under § 30-143, and civil penalties up to $2,500.00 per day under § 30-144, with each day of continued violation a separate offense.

Frequently Asked Questions

When do I need an erosion control permit in unincorporated Effingham County?
Section 30-132(a) requires a permit from the developmental services department before starting land-disturbing activity, unless the project falls under an exemption in § 30-113, such as construction of a single-family home disturbing less than one acre outside a larger common plan of development.
How much does the permit cost?
Section 30-132(c) sets a fee of $40.00 for each acre or fraction of an acre in the project area, plus a separate state fee under O.C.G.A. § 12-5-23(a)(5) capped at $80.00 per acre, both due before permit issuance.
What happens if erosion controls aren't maintained?
Section 30-142 requires a written warning with five days to correct a first or second violation before a stop-work order issues; a third violation brings an immediate stop-work order, and § 30-144 allows civil penalties up to $2,500.00 per day of continued violation.

Sources & Official References

Other rules in Effingham County

All Effingham County rules

Compare Effingham County to another location·View the Georgia environmental rules overview

Get notified when Erosion Control in Effingham County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.