Effingham County, GA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Freeboard margin
- 1 foot above base flood elevation
- No BFE data available
- 3 feet above highest adjacent grade
- Manufactured home piers
- Minimum 36 inches above grade
- Certification required
- Licensed surveyor/engineer, referenced to NAVD 88
- Datum used
- North American Vertical Datum of 1988
Summary
New construction and substantial improvements in an unincorporated Effingham County flood hazard area must have the lowest floor elevated at least one foot above the base flood elevation, the county's built-in freeboard margin above FEMA's mapped flood level.
(1)New construction and/or substantial improvements. Where base flood elevation data are available, new construction and/or substantial improvement of any structure or manufactured home shall have the lowest floor, including basement, elevated no lower than one foot above the base flood elevation.
Full Breakdown
Sec. 34-82(1) of the county's flood damage prevention chapter (Ord. of 3-3-15, amended Ord. of 4-18-2023) requires that where base flood elevation data are available, new construction and substantial improvement of any structure or manufactured home have the lowest floor, including basement, elevated no lower than one foot above the base flood elevation, the one-foot cushion Sec. 34-5 defines as freeboard against unknown factors like wave action and urbanization effects. If solid foundation perimeter walls are used, the structure needs equalizing openings under Sec. 34-81(4).
All heating, air conditioning, electrical, ventilation, and plumbing equipment must also sit at or above that one-foot freeboard line. Sec. 34-82(2) lets non-residential structures floodproof instead of elevate, but the design must be watertight to one foot above base flood elevation and certified by a registered professional engineer or architect. Sec. 34-82(3) applies the same one-foot freeboard to manufactured homes and, for units in existing manufactured home parks, adds a 36-inch minimum pier height above grade. Where FEMA has not mapped base flood elevation data, Sec.
34-83(3) instead requires the lowest floor elevated at least three feet above the highest adjacent grade, and Sec. 34-84 applies the Sec. 34-82 elevation standard to zones with established base flood elevations but no floodway. A registered land surveyor or professional engineer must certify the as-built lowest-floor elevation to the county engineer under Sec. 34-47(2), referenced to NAVD 88, before the project can proceed past that stage; work done before certification is submitted proceeds at the permit holder's own risk.
Violations & Fines
Building below the required one-foot freeboard, or without the as-built elevation certification required under Sec. 34-47(2), is a violation presumed under Sec. 34-5's definition of 'violation' until compliance evidence is provided, and is punishable as a misdemeanor under Sec. 34-13, with each day of noncompliance a separate offense plus all case costs and expenses.
Frequently Asked Questions
How high above base flood elevation must I build in unincorporated Effingham County?
What if my parcel has no mapped base flood elevation data?
Who certifies that my structure meets the elevation requirement?
Sources & Official References
Other rules in Effingham County
Compare Effingham County to another location·View the Georgia environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.