Key Facts

Trigger threshold
1 acre or more of land disturbance
Enforcing agency
Dept. of Stormwater Management (DSM)
Required plan
Approved SWP3 before disturbance begins
Max civil penalty
$2,500 per violation, per day

Summary

Fort Wayne requires a land disturbance permit and an approved stormwater pollution prevention plan before any grading, clearing, or excavation of one acre or more inside the city's Stormwater Management District.

It shall be required that a Notice of Intent (NOI) be submitted to the Indiana Department of Environmental Management and to the DSM and that a Stormwater Pollution Prevention Plan (SWP3) be submitted and approved by the DSM for any project located within the Fort Wayne Stormwater Management District that includes clearing, grading, excavation, filling and other land disturbing activities resulting in the following: (1) The disturbance of one acre or more of total land area as determined in § 53.13.

Source: Fort Wayne Planning ServicesView official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-60: Supplement contains: Local legislation current through Ord. G-19-26, passed 7-14-26, and Res. 83-19, passed 12-17-19 State legislation current through Legislative Service, 2025 Acts, Pamphlet No. 3).

Full Breakdown

Under City Code § 53.11, any project inside the Fort Wayne Stormwater Management District that clears, grades, excavates, or fills one acre or more of land, or is part of a larger common plan of development reaching one acre, must have a Stormwater Pollution Prevention Plan (SWP3) approved by the Department of Stormwater Management before land disturbance begins, plus a Notice of Intent filed with IDEM. The project site owner must then obtain a land disturbance permit under § 53.14 and follow the erosion and sediment control standards in § 53.15 throughout construction.

Violations & Fines

Violations draw a Notice of Violation, a stop-work order, and suspension of stormwater system access; civil penalties reach $2,500 per violation per day, with each day a separate offense (§ 53.70).

Frequently Asked Questions

Does every construction site need this permit?
Only sites disturbing one acre or more, or smaller lots that are part of a larger development plan totaling one acre or more; standalone lots under an acre outside such a plan aren't covered.
Who reviews and approves the plan?
Fort Wayne's Department of Stormwater Management (DSM) reviews the SWP3 and issues the land disturbance permit under Municipal Code Chapter 53, separate from zoning review.

Sources & Official References

Other rules in Fort Wayne

All Fort Wayne rules

Compare Fort Wayne to another location·View the Indiana environmental rules overview

Get notified when Erosion Control in Fort Wayne, IN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.