Fruitport Charter Township, MI Environmental Rules: Erosion Control (2026)
Key Facts
- Permit authority
- Township planning commission
- Filing fee
- $150.00
- Inspection fee
- $25.00, inspections every six months
- Bank slope limit
- Five feet horizontal to one foot vertical
- Topsoil recovery
- Minimum of four inches
- State reference
- MCL 324.9101 et seq.
Summary
In Fruitport Charter Township (outside the Village of Fruitport), Code § 42-180 requires a planning commission permit to dump, remove or strip soil, except grading incidental to a building permit, and requires every excavated or filled site to be landscaped so that all soil erosion by wind and water is eliminated. The section closes with a reference to state law, MCL 324.9101 et seq.
(b) Permit required. It shall be unlawful for any persons to dump, remove, or strip any soil or other material without a permit from the township planning commission. No permit will be required where the moving, grading or leveling of the aforesaid materials is carried on for the immediate use or development of land upon which these substances are found or where the removal or dumping is incidental to the construction or alteration of a building or the premises, pursuant to a building permit issued by the building inspector. However, where major reshaping of the land is contemplated either by removal or dumping, the aforesaid permit shall be required. ... m. The site shall be so landscaped upon completion of each excavated or filled part of the site, that all soil erosion by wind and water will be eliminated. ... State law reference--Soil erosion and sedimentation control, MCL 324.9101 et seq.
Full Breakdown
Section 42-180 is the township code section that carries the erosion language, inside its rules for soil removal, sand and gravel mining and related land use activities. Its stated intent is to protect public health, safety and welfare, preserve natural resources and prevent nuisances and hazards.
The permit comes first. It is unlawful to dump, remove or strip any soil or other material without a permit from the township planning commission. No permit is required where the moving, grading or leveling is for the immediate use or development of the land where the material is found, or where it is incidental to construction or alteration of a building under a building permit issued by the building inspector. Major reshaping of the land, by removal or dumping, still requires the permit. The application goes to the township clerk in quadruplicate, with the original sworn, along with a topographic map covering a 300-foot radius, a filing fee of $150.00 and a permit fee of $25.00 for inspections, which happen at each six-month period of operation. The planning commission requires a surety bond and a certificate of insurance, and holds a public hearing on the application within 30 days of filing.
The permit then carries working standards. Bank slopes cannot be steeper than five feet horizontal to one foot vertical, extended into any ponded water to a depth of three feet. Haul roads within 300 feet of an occupied residence are kept dust free. In stripping, enough topsoil is stockpiled to recover the entire site with a minimum of four inches of topsoil, replaced as work progresses if stripping runs longer than 30 days. Dumped parcels are graded within six months to prevent water collecting, and nothing is dumped on spillways or floodplains without planning commission approval after a public hearing. The site must be landscaped after each excavated or filled part so that all soil erosion by wind and water is eliminated.
A permit that is not started within six months expires, and the planning commission can revoke it after a hearing on five days' notice. Buffer berms elsewhere in Chapter 42, including § 42-184(b)(7), must have slopes sufficiently gradual to prevent erosion.
Violations & Fines
Failing to meet permit conditions can lead to suspension by the building inspector pending a hearing, and to revocation by the planning commission after five days' notice. An unprotected open or dangerous excavation is declared a public nuisance: the owner gets written notice and at least 30 days to abate, and if no appeal is made within ten days the township can do the work and assess the cost against the property. Chapter 42 violations are also civil infractions under § 42-5.
Frequently Asked Questions
Do I need a permit to grade my lot for a new house in Fruitport Township?
What does the township require to stop erosion at an excavation site?
How much does an excavation permit cost?
How long is the permit good if I do not start work?
Sources & Official References
Other rules in Fruitport Charter Township
Compare Fruitport Charter Township to another location·View the Michigan environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.