Key Facts

Governing code
UDC § 33-7.4.2(2)
Trigger
During and after new construction
Design standard
Subdivision Public Improvements Standards Manual
Exceptions
Public works director approval, in writing only
Large-site runoff cap
10-yr post-dev rate at or below pre-dev rate

Summary

Jefferson Parish requires erosion and sediment controls on every development its stormwater rules cover, not just a single high-risk category. Section 33-7.4.2(2) of the Unified Development Code's adequate-public-facilities article makes controls mandatory during and after new construction whenever they are needed to keep erosion or downstream sediment deposits from increasing.

These county ordinances apply to unincorporated areas of Jefferson Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(1)On-site stormwater detention or retention basins shall be required where needed to protect public or private property from increased volumes or velocity of stormwater runoff.(2)Erosion and sedimentation controls shall be required during and after new construction as needed to prevent increased erosion or increased deposits of material downstream from the development.(3)Stormwater systems shall be designed to minimize future operational and maintenance expenses.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 20 Update 2).

Full Breakdown

Article 7 of Jefferson Parish's Unified Development Code, Adequate Public Facilities, ties every development approval to the parish's stormwater design standards. 1 requires development to be laid out for proper drainage using curb and gutter, catch basins, canals, culverts, bridges, natural waterways, and stormwater best management practices sized to accommodate runoff from the entire upstream drainage area, not merely the parcel being developed. 2 builds the erosion-specific mandate on top of that design standard: on-site detention or retention basins are required wherever needed to protect public or private property from increased stormwater volume or velocity, and erosion and sedimentation controls are required both during and after new construction whenever needed to prevent increased erosion or increased sediment deposits downstream of the site.

The design itself must follow the Jefferson Parish Subdivision Public Improvements Standards Manual, and only the public works director can grant an exception, and only in writing. 4 requires non-residential developments of ten thousand square feet or more, and single-family developments of five acres or more, to hold their ten-year-storm post-development runoff rate at or below the pre-development rate, typically through on-site detention. 13.

Violations & Fines

Erosion and sedimentation control is a condition of development approval, not an afterthought: the public works director must approve any deviation from the Subdivision Public Improvements Standards Manual in writing before construction, and Section 33-7.1.13 blocks a building permit until the parish or its authorized agent inspects and accepts the required public improvements, including drainage and erosion-control work built to the manual's specifications.

Frequently Asked Questions

Does Jefferson Parish require erosion control during construction?
Yes. Section 33-7.4.2(2) of the Unified Development Code requires erosion and sedimentation controls during and after new construction whenever they are needed to prevent increased erosion or increased downstream sediment deposits, and the design must follow the Jefferson Parish Subdivision Public Improvements Standards Manual.
Who can approve a different erosion-control design than the parish manual requires?
Only the public works director, and only in writing. Section 33-7.4.2 states the director must grant exceptions to these requirements in writing, so an unwritten or verbal sign-off does not satisfy the code.
Do small residential lots face a runoff limit too?
The numeric ten-year-storm runoff cap in Section 33-7.4.4 applies to non-residential developments of 10,000 square feet or more and single-family developments of five acres or more; smaller residential lots still owe erosion and sedimentation controls under Section 33-7.4.2 but are not subject to that specific detention-basin runoff calculation.

Sources & Official References

Other rules in Jefferson Parish

All Jefferson Parish rules

Compare Jefferson Parish to another location·View the Louisiana environmental rules overview

Get notified when Erosion Control in Jefferson Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.