Key Facts

BMPs required
Silt fences, diversions, sediment traps
Stabilization deadline
14 days after disturbance ends
Temporary BMP removal
Within 30 days of permanent vegetation
Reach of the rule
Any nonagricultural site, any size (§109-353)
Max criminal fine
$1,000.00 per day, petty offense

Summary

Before grading starts on a construction site in unincorporated Kankakee County, § 109-351 requires silt fences, sediment traps or similar BMPs to keep sediment on site. Disturbed ground must be stabilized with vegetation within 14 days of the last disturbance, and the temporary controls stay in place, fully maintained, until permanent vegetation takes hold.

These county ordinances apply to unincorporated areas of Kankakee County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Appropriate BMPs such as silt fences, diversions, sediment traps, or other appropriate sediment or runoff control measures shall be implemented to prevent the release of sediment from construction sites prior to the commencement of grading activities. ... Disturbed areas sh ... all be stabilized with approved vegetative measures within 14 calendar days following the end of active disturbance or redisturbance. All temporary soil erosion and sediment control BMPs shall remain in place, and be fully maintained, until the establishment of permanent vegetation throughout the construction site at which time they shall be removed within 30 days.

Full Breakdown

Kankakee County Code § 109-351, part of the Construction Site Runoff Control division of the stormwater ordinance (Ord. No. 2006-04-11-78), requires appropriate BMPs such as silt fences, diversions and sediment traps before grading activities begin on any construction site in unincorporated Kankakee County, so sediment does not leave the site. The owner must minimize disturbed area, protect and stabilize disturbed soil, and manage construction entrances so sediment is not tracked onto public roads; any sediment that is tracked onto a street must be removed immediately.

Disturbed areas must be stabilized with approved vegetative measures within 14 calendar days after active disturbance or redisturbance ends, and temporary erosion and sediment control BMPs must stay in place and be fully maintained until permanent vegetation is established, after which they must come out within 30 days. Section 109-353 lets the county reach any nonagricultural construction activity, no matter its size, if it is causing or contributing to erosion, sediment or stormwater problems. The site's owner is responsible for compliance under § 109-348, and § 109-352 keeps that duty running to future owners through later maintenance or construction on the same site.

These erosion control duties apply on top of, not instead of, the grading and drainage permit thresholds in division 2 of the same article, which require a site plan and BMP details for most disturbances over 5,000 square feet.

Violations & Fines

Under § 109-267, the planning director can post a stop-work order at the site barring further construction and inspections until sediment controls are fixed, and county crews may enter to abate an erosion violation at the owner's expense. Section 109-268 makes a violation a petty offense with a fine up to $1,000.00 and each day counted as a separate offense.

Frequently Asked Questions

What erosion controls does Kankakee County require on a construction site?
Silt fences, diversions, sediment traps or other appropriate sediment or runoff control measures, put in place before grading begins so sediment does not leave the site. Section 109-351 also requires managing construction entrances so equipment does not track sediment onto public roads.
How fast do I have to stabilize disturbed soil in unincorporated Kankakee County?
Within 14 calendar days of the end of active disturbance or redisturbance, § 109-351 requires disturbed areas to be stabilized with approved vegetative measures, and temporary BMPs must stay fully maintained until permanent vegetation is established across the whole construction site.
Can the county require erosion controls on a small project that would otherwise be exempt?
Yes. Under § 109-353, the county can require any nonagricultural construction activity to comply with the erosion and sediment control rules, regardless of its disturbed area or type, once it is found to be causing or contributing to an erosion or stormwater problem.

Sources & Official References

Other rules in Kankakee County

All Kankakee County rules

Compare Kankakee County to another location·View the Illinois environmental rules overview

Get notified when Erosion Control in Kankakee County, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.