Key Facts
- BMPs required
- Silt fences, diversions, sediment traps
- Stabilization deadline
- 14 days after disturbance ends
- Temporary BMP removal
- Within 30 days of permanent vegetation
- Reach of the rule
- Any nonagricultural site, any size (§109-353)
- Max criminal fine
- $1,000.00 per day, petty offense
Summary
Before grading starts on a construction site in unincorporated Kankakee County, § 109-351 requires silt fences, sediment traps or similar BMPs to keep sediment on site. Disturbed ground must be stabilized with vegetation within 14 days of the last disturbance, and the temporary controls stay in place, fully maintained, until permanent vegetation takes hold.
Appropriate BMPs such as silt fences, diversions, sediment traps, or other appropriate sediment or runoff control measures shall be implemented to prevent the release of sediment from construction sites prior to the commencement of grading activities. ... Disturbed areas sh ... all be stabilized with approved vegetative measures within 14 calendar days following the end of active disturbance or redisturbance. All temporary soil erosion and sediment control BMPs shall remain in place, and be fully maintained, until the establishment of permanent vegetation throughout the construction site at which time they shall be removed within 30 days.
Full Breakdown
Kankakee County Code § 109-351, part of the Construction Site Runoff Control division of the stormwater ordinance (Ord. No. 2006-04-11-78), requires appropriate BMPs such as silt fences, diversions and sediment traps before grading activities begin on any construction site in unincorporated Kankakee County, so sediment does not leave the site. The owner must minimize disturbed area, protect and stabilize disturbed soil, and manage construction entrances so sediment is not tracked onto public roads; any sediment that is tracked onto a street must be removed immediately.
Disturbed areas must be stabilized with approved vegetative measures within 14 calendar days after active disturbance or redisturbance ends, and temporary erosion and sediment control BMPs must stay in place and be fully maintained until permanent vegetation is established, after which they must come out within 30 days. Section 109-353 lets the county reach any nonagricultural construction activity, no matter its size, if it is causing or contributing to erosion, sediment or stormwater problems. The site's owner is responsible for compliance under § 109-348, and § 109-352 keeps that duty running to future owners through later maintenance or construction on the same site.
These erosion control duties apply on top of, not instead of, the grading and drainage permit thresholds in division 2 of the same article, which require a site plan and BMP details for most disturbances over 5,000 square feet.
Violations & Fines
Under § 109-267, the planning director can post a stop-work order at the site barring further construction and inspections until sediment controls are fixed, and county crews may enter to abate an erosion violation at the owner's expense. Section 109-268 makes a violation a petty offense with a fine up to $1,000.00 and each day counted as a separate offense.
Frequently Asked Questions
What erosion controls does Kankakee County require on a construction site?
How fast do I have to stabilize disturbed soil in unincorporated Kankakee County?
Can the county require erosion controls on a small project that would otherwise be exempt?
Sources & Official References
Other rules in Kankakee County
Compare Kankakee County to another location·View the Illinois environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.