Lakewood, NJ Environmental Rules: Erosion Control (2026)
Key Facts
- Permit required
- Land disturbance permit, Code Enforcement & Zoning
- Application fee
- $100 first acre, $15 each additional acre
- Review period
- 30 days, extendable 30 more days
- Penalty
- $25-$3,000 per violation, per day
- Bond
- 1-year maintenance bond required
- Appeal deadline
- 10 days to Township Committee
Summary
Lakewood Township requires a land disturbance permit before any grading, clearing or soil disturbance begins under Code § 30-5.1. The Department of Code Enforcement and Zoning approves an erosion and sediment control plan meeting state Standards, charges $100 for the first acre and $15 per additional acre, and can fine violators $25 to $3,000 a day.
No land area shall be disturbed by any person within this Township unless the applicant has submitted to the Department Head of the Department of Code Enforcement and Zoning or his designee a plan to provide for soil erosion and sediment control for such land area in accordance with the Standards, and such plan has been approved, and a valid land disturbance permit has been issued by the Department Head of the Department of Code Enforcement and Zoning or his designee except as exempted by Section 30-7.
Full Breakdown
Township of Lakewood Code Chapter 30 runs the township's own soil erosion and sediment control program through the Department of Code Enforcement and Zoning rather than the state directly. 1 bars any land disturbance in the township until the applicant files a soil erosion and sediment control plan with the Department Head of Code Enforcement and Zoning and receives a land disturbance permit; the applicant may consult the Ocean County Soil Conservation District when choosing control measures. 3 gives the township 30 days to review a complete application, extendable another 30 days by written agreement, and treats a missed deadline as automatic certification.
1 lists the design principles a plan must satisfy: minimizing soil exposure and its duration, retaining natural vegetation where feasible, using temporary seeding or mulching on exposed critical areas, accommodating increased runoff, and installing sediment basins and diversions before any grading starts. 3 requires a maintenance bond covering the work for one year after completion or until the Soil Specialist certifies the measures are permanently stabilized. 4 sets the fee at $100 for the first acre or part of an acre and $15 for each additional acre.
Section 30-7 exempts land disturbance tied to existing one- and two-family dwellings, home gardening for personal consumption, and agricultural use under an approved farm conservation plan. 7 until the Soil Specialist confirms compliance, and a copy of that report goes to the Ocean County Soil Conservation District.
Violations & Fines
Violating Chapter 30 draws a civil penalty of $25 to $3,000 per offense under the Penalty Enforcement Law, N.J.S.A. 2A:58-1 et seq., collectible in Municipal Court or Superior Court, Special Civil Part. Section 30-6.6 lets the township or the Ocean County Soil Conservation District issue a stop-construction order for deviating from the certified plan, halting all further work until the site is back in compliance. Each day a violation continues counts as a separate offense.
Frequently Asked Questions
Do I need a permit before grading a lot in Lakewood Township?
What does an erosion control permit cost in Lakewood?
Is my own home exempt from Lakewood's erosion control rules?
What happens if I ignore a stop-construction order?
Sources & Official References
Other rules in Lakewood
Compare Lakewood to another location·View the New Jersey environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Erosion Control in Nearby Cities
How other cities in this county handle erosion control.