Louisville, KY Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Enforcing agency
Metropolitan Sewer District (MSD)
Permit required
EPSC plan + site disturbance permit
Max civil fine
$4,000 per violation, per day
Appeal body
EPSC Board hearing within 14 days
Governing chapter
Metro Code Ch. 159

Summary

Louisville Metro requires a Metropolitan Sewer District site disturbance permit before any clearing, grading, or land-disturbing construction begins, under the Erosion Prevention and Sediment Control Ordinance.

No land disturbing activity subject to the provisions of this chapter shall take place except in accordance with either: (a) An approved EPSC plan and a duly-issued site disturbance permit; or (b) An authorized general permit.

Source: Louisville MSD — Development ServicesView official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-47: Supplement contains: Local legislation current through Ordinances passed by the Council and approved by the Mayor as of July 1, 2026).

Full Breakdown

Under Chapter 159 of the Metro Code, no land disturbing activity, clearing, grading, excavating, or filling, may proceed without either an MSD-approved EPSC plan and site disturbance permit or an authorized general permit. MSD reviews and issues the permits, negotiates general permits with DPDS, and performs inspections; a Type I review applies when the work is tied to subdivisions, development plans, conditional uses, or rezonings going before the Planning Commission, Board of Zoning Adjustment, or Metro Council. MSD can revoke a permit for chapter violations, false representation, or nuisance conditions, halting work until it is reissued.

Violations & Fines

Grading without a permit or violating an approved plan draws an MSD stop-work order and notice of violation, plus a civil fine of up to $4,000 per violation, with each day of continued violation counted separately.

Frequently Asked Questions

Does every Louisville Metro land-disturbing project need a grading permit?
Only activity tied to subdivisions, development/conditional-use plans, or rezonings needs MSD's full site disturbance permit; smaller work may qualify instead for an authorized general permit.
Who enforces Louisville's grading and drainage rules?
The Metropolitan Sewer District reviews plans, issues permits, inspects sites, and can issue stop-work orders; contested violations go before the EPSC Board.

Sources & Official References

Other rules in Louisville

All Louisville rules

Compare Louisville to another location·View the Kentucky environmental rules overview

Get notified when Erosion Control in Louisville, KY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.