Mount Pleasant, SC Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
§ 153.043 SWPPPs
Enforcement section
§ 153.070
Civil penalty
Up to $500 per violation, per day
Stop work admin fee
$200
Inspection frequency
Every 7 or 14 days
Sediment removal trigger
50% of design capacity

Summary

In the Town of Mount Pleasant, any construction project covered by a drainage plan must have a Stormwater Pollution Prevention Plan (SWPPP) prepared by a licensed engineer that identifies erosion and sediment control measures. Those measures must stay in effective operating condition throughout construction, with site inspections at least every 7 or 14 days.

(F) Maintenance of controls. (1) All erosion and sediment control measures and other protective measures identified in the SWPPP must be maintained in effective operating condition. If site inspections identify BMPs that are not operating effectively, maintenance must be performed as soon as practical or as reasonably possible, and before the next storm event whenever practicable, to maintain the continued effectiveness of stormwater controls. ... (3) Sediment from sediment traps or sedimentation ponds must be removed as indicated in the SWPPP, or when the design capacity has been reduced by 50%, whichever occurs first.

Full Breakdown

043. Projects disturbing more than one acre need a SWPPP prepared, amended, certified and stamped by a qualified licensed individual. The plan must identify all potential pollution sources, describe practices to reduce pollutants in stormwater discharges, and include a legible site map showing drainage direction, slopes after grading, storage areas, surface waters and discharge points. Under subsection (D), the SWPPP must describe interim and permanent stabilization practices with a schedule, control measures to minimize off-site vehicle tracking of sediment onto paved surfaces, and measures addressing dust generation.

Subsection (F) requires that all erosion and sediment control measures identified in the SWPPP be maintained in effective operating condition; if inspections find a BMP not working, maintenance must happen as soon as practical and before the next storm event whenever practicable. Sediment must be removed from traps or ponds when design capacity is reduced by 50% or as the SWPPP specifies, whichever comes first. Subsection (I) sets inspection frequency at least once every 7 calendar days, or once every 14 days plus within 24 hours after a storm of a half-inch or more, dropping to monthly once a site is temporarily stabilized; inspections must be run by qualified personnel meeting DHEC-recognized training or certification. 070.

Violations & Fines

Violating any provision of Chapter 153, including the erosion and sediment control requirements of § 153.043, carries a civil penalty of not more than $500 per violation, with each day counted as a new separate violation. Written notice of a violation issues within 15 days and states the nature of the violation, proposed penalty, and correction period. The town can also impose a stop work order with a $200 administrative fee, suspend or revoke a site clearing and grading permit, or pursue injunctive relief and criminal misdemeanor prosecution in magistrate's court for negligent, willful or intentional violations.

Frequently Asked Questions

Does Mount Pleasant require an erosion control plan for construction?
Yes. Any construction project submitted with a drainage plan must include a Stormwater Pollution Prevention Plan under Mount Pleasant Code of Ordinances § 153.043, describing the erosion and sediment control measures (BMPs) that will be used and maintained through final site stabilization.
How often must a construction site be inspected for erosion control in Mount Pleasant?
At least once every 7 calendar days, or once every 14 days combined with an inspection within 24 hours after any storm event producing a half-inch of rain or more, per § 153.043(I). Frequency can drop to monthly once the site is temporarily stabilized.
What happens if erosion control measures fail on a Mount Pleasant site?
Under § 153.043(F), any BMP found not operating effectively during an inspection must be repaired or replaced as soon as practical and before the next storm event whenever practicable, and sediment traps or ponds must be cleaned out once capacity drops by 50%.
What is the penalty for violating Mount Pleasant's erosion control rules?
Section 153.070 sets a civil penalty of up to $500 for each violation, with every day of continued violation treated as a separate offense, on top of possible stop work orders, permit revocation, or criminal misdemeanor charges for willful violations.

Sources & Official References

Other rules in Mount Pleasant

All Mount Pleasant rules

Compare Mount Pleasant to another location·View the South Carolina environmental rules overview

Get notified when Erosion Control in Mount Pleasant, SC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Charleston County handle erosion control.

Charleston, SC
Some Restrictions
North Charleston, SC
Some Restrictions