Plano, TX Environmental Rules: Erosion Control (2026)
Key Facts
- Trigger threshold
- 5,000+ sq. ft. disturbed
- Plan required before
- even projects needing no building permit
- Residential deposit
- $100 per lot
- Reinspection fee if noncompliant
- $150
- Cure period
- 24 hours
- Governing section
- Code of Ordinances § 14-93
- Adopted by
- Ord. No. 98-3-9 (3-16-1998)
Summary
Anyone conducting construction or land-disturbing activity in Plano, disturbing 5,000 square feet or more of vegetative ground cover, must prepare and get city approval of an erosion control plan before work begins, whether or not a building permit is otherwise required, under Code of Ordinances § 14-93.
(a)Application of article. A responsible party engaging in any land disturbing activity or any construction activities shall prepare an erosion control plan and submit that plan to the city for approval. This article shall apply regardless of whether a responsible party is required to obtain a permit from the city in order to conduct such land disturbing or construction activity. The responsible party shall also be held liable for violations of this article committed by third parties engaging in activities related to the responsible party's project;(b)Erosion control plan implementation and compliance. Each responsible party shall implement and maintain the erosion control measures shown on its approved erosion control plan in order to minimize the erosion and the transport of silt, earth, topsoil, etc., by water runoff or construction activities, beyond the limits of the responsible party's site onto city streets, drainage easements, drainage facilities, storm drains or other city property prior to beginning any land disturbing activity.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 153).
Full Breakdown
Plano's erosion control article, Chapter 14, Article VI, applies to any 'responsible party', a business entity, franchised utility, developer, property owner, contractor, or permit holder, engaged in construction activities or 'land disturbing activity,' defined in § 14-92 as excavation, planting, tilling, or grading that exposes 5,000 or more square feet of natural or improved ground cover to erosive forces, including all franchise-utility installation and maintenance work. Section 14-93(a) requires the responsible party to prepare an erosion control plan and submit it to the city for approval before beginning the activity, and this duty applies 'regardless of whether a responsible party is required to obtain a permit from the city' for the underlying work, meaning even utility trenching or grading that needs no building permit still triggers the plan requirement.
Once approved, § 14-93(b) requires implementation and maintenance of the erosion measures shown on the plan to keep silt, earth, and topsoil from leaving the site onto city streets, drainage easements, storm drains, or other city property, and the responsible party is liable for violations committed by third parties working on its project. Off-site borrow areas, spoil areas, and construction staging areas count as part of the project site under § 14-93(c), and permanent erosion control must be established on all related land areas before final occupancy or subdivision acceptance under § 14-93(d).
Residential subdivision developers additionally post a $100-per-lot erosion control deposit before final plat approval (§ 14-96), and noncompliant sites get a 24-hour cure period before the city deducts a $150 reinspection fee, issues a stop work order, and cites each violation (§ 14-96(d)). Farming and ranching land-disturbing activity must separately submit a plan under § 14-98. The article traces to Ordinance No. 98-3-9, adopted March 16, 1998.
Violations & Fines
A responsible party that begins land-disturbing or construction activity without a city-approved erosion control plan, or fails to implement and maintain the approved plan's erosion measures, is in violation of § 14-93. For residential subdivisions the city gives 24 hours to cure noncompliance before deducting a $150 reinspection fee from the developer's erosion control deposit under § 14-96(d) and, if still noncompliant, issuing a stop work order and a citation for each violation.
Frequently Asked Questions
Does every Plano construction project need an erosion control plan?
Who is responsible for erosion control violations on a Plano job site?
How much is the erosion control deposit for a new subdivision in Plano?
What happens if erosion control devices aren't maintained on a Plano site?
Sources & Official References
Other rules in Plano
Texas rules heatmap·Compare Plano to another location·View the Texas environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Erosion Control in Nearby Cities
How other cities in Collin County handle erosion control.