Santa Fe, NM Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
Grading/clearing over 5,000 sq ft or arroyo work
Stabilization deadline
21 days after construction ends
Required temporary devices
Silt fencing, straw bales, berms, sediment traps
Tree protection setback
Fencing 5 feet outside dripline
Dust control trigger
Disturbance over 5,000 sq ft
Enforcing officials
City engineer and land use director
Compliance gate
No certificate of occupancy until inspected

Summary

Santa Fe requires a construction permit for grading on most disturbed sites and mandates specific erosion and sediment control devices before land can be cleared. The city engineer enforces silt fencing, sediment traps, and stabilization deadlines under Section 14-8.2 of the Land Development Code.

(7)Best Management Practices. The following best management practices shall be used before and during the construction process:(a)disturbed areas shall be protected from erosion during construction by diverting stormwater around the disturbed area, dissipating the energy of stormwater adequate to prevent erosion, retaining sediment on the disturbed area or other means adequate to retain soil on site, or a notice of intent (NOI) is filed;(b)except as necessary to install temporary erosion and sediment control devices, land shall not be graded or cleared of vegetation until all such temporary devices have been properly installed and inspected. Temporary erosion and sediment control devices may include silt fencing, swales, straw bales, berms, geotextiles, sediment basins or traps and fencing. Control devices shall be kept in place and functional until the disturbed area is permanently stabilized; or notice of termination (NOT) is filed;

Full Breakdown

2(D)(7), the city's terrain and stormwater management chapter, builders must protect disturbed areas from erosion by diverting stormwater around the site, dissipating runoff energy, or retaining sediment on-site, unless a federal Notice of Intent (NOI) is filed instead. Except when installing the devices themselves, no grading or vegetation clearing may begin until temporary erosion and sediment control devices, which the code lists as silt fencing, swales, straw bales, berms, geotextiles, and sediment basins or traps, are installed and inspected. Those devices must stay in place and functional until the disturbed area is permanently stabilized or a Notice of Termination (NOT) is filed.

Significant trees and undisturbed vegetation must be fenced off before any heavy machinery moves on-site, with fencing set five feet outside the tree dripline. Soil stockpiles need protection from wind and water erosion, and projects disturbing more than 5,000 square feet must control dust, typically by watering exposed ground. 2(D)(5) sets a hard deadline: soil stabilization and erosion control measures for all disturbed land must be completed within 21 days after construction activity ends, though planting can wait for the next suitable season if temporary measures stay maintained in the meantime.

2(E)). The land use director and city engineer administer the program, and no certificate of occupancy is issued until the parcel is in full compliance and all required inspections are documented.

Violations & Fines

Section 14-8.2(I) requires the applicant to schedule inspections when erosion and sediment control devices are installed, when stormwater measures are complete, and when site restoration is finished; further construction or permit issuance stops until the inspector gives written approval. The land use director may enter any property under this section to check compliance. If maintenance violations go uncorrected after notice, the city may perform the work itself and bill the owner or responsible party for the cost (Section 14-8.2(K)(3)).

Frequently Asked Questions

Does Santa Fe require an erosion control permit for construction?
Yes. A construction permit for grading is required under Section 14-8.2(E) when work occurs in an arroyo or drainageway, removes more than 25% of significant trees or grass cover, or disturbs more than 5,000 square feet through clearing and grading. Driveway and road grading and utility trenching for commercial or public projects also trigger the permit.
What erosion control devices does Santa Fe's code require?
Section 14-8.2(D)(7)(b) lists silt fencing, swales, straw bales, berms, geotextiles, and sediment basins or traps as acceptable temporary devices. Land cannot be graded or cleared until these are installed and inspected, and they must remain functional until the disturbed area is permanently stabilized or a Notice of Termination is filed.
How long do builders have to stabilize a site after construction?
Section 14-8.2(D)(5) gives 21 days after construction or other soil-disturbing activity ends to complete soil stabilization and erosion control measures. If the season is wrong for planting, stabilization can be delayed to the next planting season, but temporary erosion control must stay maintained until then.
Who inspects erosion control compliance in Santa Fe?
The land use director schedules and conducts the required inspections under Section 14-8.2(I), checking that erosion and sediment control devices are in place, that stormwater measures are completed, and that final site restoration is done. No further construction or permits proceed until the inspector approves each stage in writing.

Sources & Official References

Other rules in Santa Fe

All Santa Fe rules

Compare Santa Fe to another location·View the New Mexico environmental rules overview

Get notified when Erosion Control in Santa Fe, NM changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.