Key Facts

BMP duty
Every construction site operator
Stabilization
Within 14 days of work stoppage
SWPPP + NOI
Required at 5+ acres
SWPPP only
Required 1 to under 5 acres
Site plan
Required with permit application
Enforcement
Occupancy certificate can be held
Fees
Set by Code § 2-009.00

Summary

St. Tammany Parish requires every construction site in the unincorporated parish, from single-family lots to subdivisions, to install and maintain Best Management Practices controlling silt, sediment, mud and clay discharge under its MS4 stormwater ordinance. Projects need an approved Stormwater Agreement and Construction Stormwater Site Plan before a building, site work or subdivision permit issues, plus an LDEQ SWPPP for sites disturbing an acre or more.

These county ordinances apply to unincorporated areas of St. Tammany Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

F.Stormwater Discharges from Construction Activities.1.No construction activity nor development shall degrade water quality in the receiving stream or adversely affect the MS4.2.All construction projects involving site work of any kind, including but not limited to subdivision development, minor subdivision development, residential construction, commercial construction, and roadway construction shall comply with the stormwater pollution prevention requirements of this section.3.All appropriate parish permits shall be obtained before the commencement of construction.4.All operators of construction sites shall use appropriate Best Management Practices or BMPs to control discharge to waterways and conveyances of the parish. Pollutants such as silt, sediment, mud, clay, and other construction contaminant materials associated with site work of any kind shall be controlled to the maximum extent practicable.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 12 Update 2).

Full Breakdown

Sec. 900-6.9(F) of the Unified Development Code makes every operator of a construction site, whether working on new residential or commercial construction, subdivision development, pool installation, pond excavation or a remodel that alters site drainage, responsible for controlling discharge to the parish's MS4, drainage infrastructure and waterways. Operators must use Best Management Practices selected from the Best Management Practices for Coastal Louisiana Nonpoint Source Pollution Handbook to keep silt, sediment, mud and clay off-site to the maximum extent practicable, and parish permits must be secured before construction starts.

An approved Stormwater Agreement, provided by the parish and signed at building-permit or site-work-permit stage, commits the owner to obtain any required LDEQ permit; subdivisions developed in phases file one at each phase's concept-plan stage. A Construction Stormwater Site Plan covering erosion control, sediment control and receiving-water impacts must accompany the permit application under Sec. 900-6.9(H). During construction, disturbed soil not actively worked must be stabilized within 14 days, BMPs must be self-inspected and repaired before the next storm, and a stabilized construction entrance/exit pad is required to keep mud off public roads. Sites of 5 acres or more (including phases of a larger common plan) need an LDEQ Notice of Intent and full SWPPP; sites between 1 and 5 acres need a SWPPP without an NOI. Capital projects run by parish personnel, life-safety emergency work, grave excavation and ordinary agricultural practices are exempt from the Stormwater Agreement and site-plan requirement, though the owner still must maintain erosion controls.

Violations & Fines

Parish stormwater inspectors check sites at the preliminary drainage inspection, at final inspection, and on an unscheduled basis; failure to correct problems after a failed inspection can trigger enforcement action under Sec. 900-6.9(J). The parish may withhold a certificate of occupancy until the final stormwater inspection confirms required controls are in place, and inspection and re-inspection fees are billed under Code of Ordinances § 2-009.00.

Frequently Asked Questions

Does a single-family home in St. Tammany Parish need an erosion control plan?
New residential construction needs an approved Construction Stormwater Site Plan and Stormwater Agreement before the building permit issues, per Sec. 900-6.9(F)(5). Accessory buildings of 200 square feet or more, pool installations and pond excavation trigger the same requirement; only exemptions like emergency work, cemetery excavation and routine agricultural practices are excused.
When does a St. Tammany Parish project need a full SWPPP and NOI?
Under Sec. 900-6.9(I)(8), any site disturbing 5 acres or more, including a lot that is part of a larger common plan of development, must file an LDEQ Notice of Intent and Stormwater Pollution Prevention Plan. Sites between 1 and 5 acres still need a SWPPP, just not the NOI filing.
How quickly must a construction site stabilize bare soil?
Sec. 900-6.9(I)(1) requires disturbed portions of a site to be stabilized within 14 days after construction activity temporarily or permanently stops there. Structural BMPs must divert flow from exposed soil in the meantime, and operators must maintain erosion and sediment controls until warranty obligations end or an occupancy certificate issues.
What can the parish do if BMPs fail during a storm?
Operators must self-inspect BMPs after storm events and repair, revise or replace them before the next one, per Sec. 900-6.9(I)(4). The parish can also hold occupancy certificates until a final stormwater inspection confirms controls are working, and any BMP change must be logged in the SWPPP within 7 calendar days.

Sources & Official References

Other rules in St. Tammany Parish

All St. Tammany Parish rules

Compare St. Tammany Parish to another location·View the Louisiana environmental rules overview

Get notified when Erosion Control in St. Tammany Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.