Summit County, OH Environmental Rules: Erosion Control (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

SWP3 trigger
1+ acre of soil disturbance
Jurisdiction
unincorporated Summit County only
Re-inspection fee
$250 per Notice of Violation
Civil fine
$100-$500 per day of violation
Appeal deadline
90 days to the Planning Commission

Summary

Summit County requires a Storm Water Pollution Prevention Plan for any project in the unincorporated county that disturbs one acre or more of soil, from subdivisions to farm building activity, under Chapter 941. The Summit Soil and Water Conservation District reviews and inspects every plan and can issue a stop-work order and pursue fines for a violation.

City-specific rules exist: Akron has its own erosion control rules that differ from Summit County's county-level regulations. If you live in Akron, check the city-specific page instead.

This Chapter requires that a Storm Water Pollution Prevention Plan (SWP3) be developed and implemented for all soil disturbing activities disturbing one or more acres of total land or will disturb less than an acre of land but are part of a larger common plan of development or sale that will ultimately disturb one or more acres of land in the unincorporated areas of the County of Summit and on which any regulated activity of Section 941.01(c) is proposed. For parcels less than one acre in size a SWP3 may not be required; however the owner shall comply with all other provisions of this chapter.

Full Breakdown

01(d) for activity already regulated under the state's Agricultural Sediment Pollution Abatement Rules. 05(a) sets the numeric trigger: a Storm Water Pollution Prevention Plan, or SWP3, must be developed and implemented for any soil-disturbing activity that disturbs one acre or more of land, or a smaller phase of a larger plan that will ultimately reach one acre; parcels under an acre may skip the SWP3 but must still follow the chapter's other rules. 06 routes the SWP3 and required fees through the Summit Soil and Water Conservation District (SWCD) and the County Engineer.

10 charges the SWCD's current fee schedule for plan review, filing and inspection, plus a $250 re-inspection fee for every Notice of Violation until the site is brought back into compliance. 15 wherever an SWP3 is required, and the bond is not released until the SWP3 is satisfied. 12 gives the SWCD inspection authority over every development site to confirm compliance with the approved plan.

Violations & Fines

Section 941.13 lets the SWCD issue an immediate stop-work order if a violator never obtained the required permits, and a notice of violation in any case; if the violation continues 30 days after the first notice and 15 more days after a second notice, the SWCD can issue a stop-work order with the County Prosecutor's approval. A Court of Common Pleas injunction under Section 941.13(e) can carry a civil fine of $100 to $500 per day, and Section 941.14 gives an aggrieved party 90 days to appeal any action to the Summit County Planning Commission.

Frequently Asked Questions

When does Summit County require an erosion control plan?
Section 941.05(a) requires a Storm Water Pollution Prevention Plan for any soil-disturbing activity in the unincorporated county that disturbs one acre or more, or a smaller phase of a project that will eventually reach one acre, and even projects under an acre must still follow the chapter's other erosion and sediment rules.
Who reviews and inspects erosion control plans in Summit County?
The Summit Soil and Water Conservation District reviews the Storm Water Pollution Prevention Plan and fees under Sections 941.06 and 941.10, and Section 941.12 authorizes the SWCD to inspect every development site to confirm it is following its approved plan.
What penalties apply for violating Summit County's erosion control rules?
Section 941.13 allows an immediate stop-work order for unpermitted work, and after repeated notices of violation the County Prosecutor can seek a Court of Common Pleas injunction carrying a civil fine of one hundred to five hundred dollars for each day the violation continues.

Sources & Official References

Other rules in Summit County

All Summit County rules

Compare Summit County to another location·View the Ohio environmental rules overview

Get notified when Erosion Control in Summit County, OH changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Summit County