Walla Walla County, WA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

SWPPP trigger
1 acre or more disturbed
Common-plan sites
smaller phases still count
Plan basis
SMMEW Chapters 3 and 7
Additional permit
state construction stormwater general permit
Erosivity waiver window
1-5 acres, June 15-Oct 15
Enforcing official
county engineer, under WWCC 14.13

Summary

Construction sites in unincorporated Walla Walla County disturbing an acre or more, including smaller sites that are part of a larger common plan, must submit a stormwater site plan and pollution prevention plan (SWPPP) under WWCC 11.07.030(C) and obtain the state's construction stormwater general permit. Operators must select and maintain erosion and sediment control best management practices that meet the state's Stormwater Management Manual for Eastern Washington.

These county ordinances apply to unincorporated areas of Walla Walla County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

C.Construction Site Runoff Control.1.Construction sites disturbing greater than or equal to one acre, including construction sites of less than one acre that are part of a common plan of development or sale that is greater than one acre, shall prepare a stormwater site plan and stormwater pollution prevention plan (SWPPP) in accordance with Chapters 3 and 7 of the SMMEW.a.Construction operators shall provide erosion and sediment control BMPs and implement source control BMPs during construction to protect water quality, reduce discharge of pollutants, and satisfy state AKART requirements. Erosion and sediment control BMPs and source control BMPs shall be selected, designed, installed, operated and maintained in accordance with the standards in the SMMEW. ... 2.Construction sites disturbing greater than or equal to one acre, including construction sites of less than one acre that are part of a common plan of development or sale that is greater than one acre, shall obtain coverage under the construction stormwater general permit issued by the State of Washington Department of Ecology.

Full Breakdown

WWCC 11.07.030 sets the county's construction and post-construction stormwater standards, and subsection C, 'Construction Site Runoff Control,' is where erosion and sediment control during building activity is addressed. Any construction site disturbing one acre or more, and any smaller site that is part of a common plan of development or sale exceeding one acre, must prepare a stormwater site plan and a stormwater pollution prevention plan (SWPPP) following Chapters 3 and 7 of the Stormwater Management Manual for Eastern Washington before work begins. Construction operators must provide erosion and sediment control BMPs and implement source control BMPs during construction to protect water quality, reduce pollutant discharge, and satisfy the state's AKART standard, all known, available and reasonable methods of prevention, control and treatment, with those BMPs selected, designed, installed, operated and maintained to the manual's standards.

Under WWCC 11.07.030(C)(1)(b), a project disturbing between one and five acres between June 15 and October 15 may instead apply for a state erosivity waiver, which excuses it from the SWPPP requirement for that certified period; work that runs past the waiver window needs either a revised waiver or a full stormwater site plan for the remaining work. Every qualifying site must also obtain coverage under the state Department of Ecology's construction stormwater general permit. Plans and SWPPPs are filed with and reviewed by the county engineer under WWCC 11.07.040, and the developer bears responsibility for construction inspection, staking and record drawings under WWCC 11.07.050.

Failure to control erosion is enforced through the civil and criminal process WWCC 11.01.070 applies to the rest of Title 11, since Chapter 11.07 violations fall under that section's enforcement scheme.

Violations & Fines

Failing to prepare the required stormwater site plan and SWPPP, or failing to install and maintain erosion and sediment control BMPs, is enforced under WWCC 11.01.070: the county engineer may issue a notice of violation and order, require a voluntary correction agreement, and impose civil penalties, with criminal penalties available under WWCC Chapter 14.13 for continued noncompliance.

Frequently Asked Questions

When does my construction project need an erosion control plan in Walla Walla County?
WWCC 11.07.030(C) requires a stormwater site plan and SWPPP once a project disturbs one acre or more, or is a smaller phase of a common plan of development exceeding one acre. You must also obtain the state's construction stormwater general permit before starting work.
Can I skip the SWPPP for a small project?
Only through the state erosivity waiver: WWCC 11.07.030(C)(1)(b) allows sites disturbing one to five acres between June 15 and October 15 to apply for a waiver instead of a SWPPP, but work extending past that window needs a revised waiver or a full plan.
Who reviews my erosion control plan?
The county engineer reviews and approves stormwater site plans and SWPPPs under WWCC 11.07.040 before construction, and the developer is responsible for inspection, staking and record drawings during construction under WWCC 11.07.050.

Sources & Official References

Other rules in Walla Walla County

All Walla Walla County rules

Compare Walla Walla County to another location·View the Washington environmental rules overview

Get notified when Erosion Control in Walla Walla County, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.