Washington County, WI Environmental Rules: Erosion Control (2026)
Key Facts
- Permit trigger
- 4,000 sq ft or more of land disturbance
- Sediment standard
- Max 5 tons of sediment per acre per year
- Administering agency
- Land Conservation Committee / Land and Water Conservation Division
- Penalty
- $50-$500 forfeiture per violation, per day
- Coverage
- Applies to unincorporated Washington County lands only
Summary
Washington County requires an erosion and runoff control permit before any land-disturbing construction activity that disturbs 4,000 square feet or more, and the approved erosion control plan must hold sediment discharge to no more than five tons per acre per year until the site is stabilized.
Disturbs 4,000 square feet or more of total land surface area; or ... For sites that disturb one acre or more of total land surface area, an erosion control plan shall by design achieve a runoff discharge of no more than five tons of sediment per acre per year from sheet and rill erosion during land-disturbing activities as compared with no sediment or erosion controls, until the site is stabilized in accordance with approved models and BMP design standards identified in § 238-11 of this chapter. ... Forfeiture. Any violator shall be subject to a forfeiture of not less than $50 or more than $500, plus the cost of prosecution, for each violation. Each day that a violation exists shall constitute a separate offense.
Full Breakdown
Chapter 238 of the Code of Washington County, adopted under §§ 59.693 and 281.33, Wis. Stats., applies to all unincorporated lands in the County unless a town enforces its own equivalent ordinance or has an intergovernmental agreement with the County for administration. The Land Conservation Committee, through the Land and Water Conservation Division of the Planning and Parks Department, administers the chapter.
Section 238-6A triggers the construction-site erosion control permit whenever land-disturbing activity meets any of five thresholds: disturbing 4,000 square feet or more of land surface; excavating or filling more than 400 cubic yards; disturbing 300 linear feet of roadway ditch or open drainage channel; maintaining an existing stormwater best management practice; or any other activity the administering authority determines carries a high risk of erosion or water pollution. Once a project crosses a threshold, § 238-7 requires the erosion control plan to hold the site's sediment discharge, by design, to no more than five tons per acre per year from sheet and rill erosion until the site is stabilized, using practices such as silt fence, diversions, sediment traps and temporary mulch; if that standard cannot be met, the plan must explain in writing why and reduce the load to the maximum extent practicable.
Certain sites are exempt or partially exempt, including one- and two-family homes disturbing less than an acre, agricultural land use, and activity already covered by shoreland or nonmetallic-mining permits. Violations are enforced by the administering authority through forfeitures, stop-work orders, permit revocation or emergency action.
Violations & Fines
Under § 238-15C(1)(a), violating any provision of Chapter 238 carries a forfeiture of not less than $50 nor more than $500 plus the cost of prosecution, with each day a violation exists counted as a separate offense. The administering authority can also issue a stop-work order, revoke the permit, or take emergency action to bring a site into compliance.
Frequently Asked Questions
Do I need a permit to grade my rural building lot in Washington County?
What sediment limit does my erosion control plan have to meet?
What happens if I don't control erosion on my construction site?
Sources & Official References
Other rules in Washington County
Compare Washington County to another location·View the Wisconsin environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.