Weber County, UT Environmental Rules: Erosion Control (2026)
Key Facts
- Permit trigger
- >5,000 sq ft disturbed or 200 cu yd cut/fill
- Reviewing office
- County engineering dept / storm sewer utility manager
- Stabilization deadline
- 14 days after grading stops
- Penalty
- Class C misdemeanor, each day separate
- Large-site threshold
- 5+ acres needs state DWQ permit instead
- Inspections
- County, state, and EPA may enter anytime
Summary
Weber County requires a stormwater construction activity permit before any excavation, grading, or land-disturbing construction in the unincorporated county that disturbs more than 5,000 square feet or moves more than 200 cubic yards of material. The county engineering department reviews the required stormwater pollution prevention plan, and moving dirt before approval is unlawful under Code § 40-3-2.
A county stormwater construction activity permit is required before any person or entity may excavate, grub and clear, grade, or perform any type of construction activity that will disrupt or cause a change in the natural landscape upon any of the following types of property located within the unincorporated county: ... Disturbs more than 5,000 square feet of land surface area; Consists of the excavation and/or fill of more than 200 cubic yards of material; or Requires a building permit for which excavation or fill is a part of the construction, and less than five acres; shall apply for a county permit. Activities involving five acres or more must get a permit from the state division of water quality.
Full Breakdown
Any excavation, grubbing, grading, or other construction activity that disrupts the natural landscape on unincorporated county land triggers Weber County's stormwater construction activity permit under Code § 40-3-2. The permit is mandatory once a project disturbs more than 5,000 square feet of land surface, moves more than 200 cubic yards of cut or fill, or requires a building permit involving excavation on a parcel under five acres. Projects of five acres or larger fall instead under a state Division of Water Quality permit. Applicants file with the county engineering department, submitting a stormwater pollution prevention plan meeting the content standards of § 40-3-4 before or with their subdivision plat, site plan, building permit, or land use permit application (§ 40-3-3).
The storm sewer utility manager reviews and approves, conditions, or denies the plan. Under § 40-3-4, the plan must describe site conditions, list best management practices such as silt fence, sediment traps, gravel construction entrances, and inlet protection, and commit to stabilizing any disturbed area within 14 days after grading work stops there, longer only if snow or frozen ground prevents seeding or if work resumes within 21 days. Section 40-3-5 requires the permittee to install those measures before construction begins and maintain them until the county accepts a notice of termination.
County engineering staff, the state water quality division, and EPA representatives may inspect the site at any time under § 40-3-6. A permit can be revoked or suspended on ten to 30 days' notice for noncompliance (§ 40-3-7), triggering a stop-work order until the plan is corrected and reissued.
Violations & Fines
Moving dirt on a site before the required permit issues is unlawful under § 40-3-2. Violating any provision of Chapter 40-3 is a Class C misdemeanor, with each day of violation a separate offense under § 40-3-8. The county may also issue a stop-work order, install or maintain erosion controls itself and bill the property owner or contractor, or draw against the posted financial guarantee. State Water Quality Act and EPA penalties can apply on top of the county citation.
Frequently Asked Questions
When does Weber County require a stormwater construction permit?
Who approves the stormwater pollution prevention plan?
What happens if I start grading before getting the permit?
How soon must disturbed ground be stabilized?
Sources & Official References
Other rules in Weber County
Compare Weber County to another location·View the Utah environmental rules overview