Auburn, AL Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Freeboard requirement
- 1 foot above base flood elevation
- Applies to
- New construction, substantial improvements
- No-BFE-data standard
- 3 feet above highest adjacent grade
- Floodproofing alternative
- Nonresidential only, engineer-certified
- Verification
- FEMA elevation certificate before occupancy
Summary
Auburn requires the lowest floor of new construction and substantially improved buildings in mapped flood hazard areas to sit at least one foot above the base flood elevation, under City Code § 7-42(1). That one-foot freeboard applies on top of FEMA's base flood elevation, and nonresidential buildings may floodproof to the same design elevation instead of elevating.
(1)Residential and nonresidential structures. Where BFE data is available, new construction, reconstruction or repairs made to a repetitive loss structure, and substantial improvement of any structure or manufactured home shall have the lowest floor, including basement, elevated no lower than one foot above the base flood elevation (also referred to as the design flood elevation). Should solid foundation perimeter walls be used to elevate a structure, openings sufficient to facilitate the unimpeded movements of flood waters shall be provided in accordance with standards of division 4, subsection 7-42(3).
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 90).
Full Breakdown
Section 7-42 sets Auburn's technical flood-hazard-reduction standards for special flood hazard areas designated A, AE and AH. ' If a builder uses solid foundation perimeter walls to achieve that elevation, the walls must include flood openings sized under § 7-42(3), at least two openings per enclosed area totaling one square inch of net opening for every square foot of enclosed floor space subject to flooding, positioned in at least two exterior walls with the lowest opening no higher than one foot above grade. Nonresidential structures may floodproof instead of elevate under § 7-42(2), but must be watertight to the same one-foot-above-BFE design elevation, with a professional engineer or architect licensed in Alabama certifying the design.
Where no BFE data exists at all (approximate A-zones), § 7-44 requires the lowest floor to sit at least three feet above the highest adjacent grade. Manufactured homes must meet the same one-foot-above-BFE elevation on a permanent, anchored foundation under § 7-42(4). The floodplain administrator verifies the as-built elevation with a FEMA elevation certificate before issuing a certificate of occupancy, per § 7-37(6).
Violations & Fines
Failing to build to the required freeboard elevation is enforced the same as any other Article II violation: a misdemeanor under § 7-27, plus a stop-work order, notice of violation and a fine of up to $500 per day and up to 180 days in jail. The floodplain administrator can also refuse to issue a certificate of occupancy until a corrected elevation certificate confirms the lowest floor meets the one-foot-above-BFE standard.
Frequently Asked Questions
How high above the base flood elevation must my house be built in Auburn?
Can a commercial building in Auburn be floodproofed instead of elevated?
What if there's no base flood elevation data for my lot?
Sources & Official References
Other rules in Auburn
Compare Auburn to another location·View the Alabama environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.