- Residential freeboard
- 3 ft above base flood elevation
- Non-residential freeboard
- 1 ft above base flood elevation
- Floodproofing option
- PE/architect FEMA certification required
- Manufactured home piers
- 36 in. minimum above grade
- AO-Zone (shallow flooding)
- 1 ft above FIRM flood depth
Summary
New residential construction in Cherokee County's future-conditions floodplain must have its lowest floor, including any basement, elevated at least three feet above the base flood elevation, one foot more than FEMA's minimum. Non-residential buildings need one foot of freeboard above base flood elevation or may floodproof instead.
New construction. New construction of principal residential structures shall not be allowed within the limits of the future-conditions floodplain unless all requirements of sections 30-38, 30-39, and 30-40 have been met. If all of the requirements of sections 30-38, 30-39, and 30-40 have been met, all new construction shall have the lowest floor, including basement, elevated no lower than three feet above the base flood elevation or one foot above the future-conditions flood elevation, whichever is higher.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 39 | Zoning: Supplement 35).
Full Breakdown
Sec. 30-57 of the Floodplain Management and Flood Damage Prevention Ordinance sets Cherokee County's freeboard standard. New construction and substantial improvement of a principal residential structure inside the future-conditions floodplain must have its lowest floor, including basement, elevated no lower than three feet above the base flood elevation or one foot above the future-conditions flood elevation, whichever is higher, once the engineering requirements of Secs. 30-38 through 30-40 are satisfied. Non-residential buildings need only one foot above base flood elevation, or may instead be floodproofed to be watertight to that height, with a licensed professional engineer or architect certifying the design on FEMA's Floodproofing Certificate and filing it with the Cherokee County Engineer.
Where solid perimeter foundation walls are used to elevate a structure, Sec. 30-56(e) requires flood vent openings of at least one square inch of net area per square foot of enclosed area, with the bottom of every opening no higher than one foot above grade, so hydrostatic forces equalize automatically. Manufactured homes get the same three-foot residential standard, or must sit on reinforced piers at least 36 inches above grade in an existing manufactured home park. For lots without established base flood data (A-Zones), Sec.
30-59 falls back to three feet above the highest adjacent grade, and Sec. 30-60 sets shallow-flooding (AO-Zone) elevations at one foot above the FIRM-specified flood depth, or three feet above grade if none is specified.
Violations & Fines
Building below the required freeboard without completing the Sec. 30-38/30-39 engineering study or the FEMA Floodproofing Certificate exposes the project to a Sec. 30-87 notice of violation, then Sec. 30-88 remedies: a stop-work order, denial of a certificate of occupancy, permit revocation, civil penalties up to $1,000.00 per day, or a Magistrate Court citation for intentional violations under Sec. 1-12.
Frequently Asked Questions
How much freeboard does Cherokee County require above base flood elevation?
Can a non-residential building be floodproofed instead of elevated?
What elevation applies to manufactured homes in Cherokee County flood zones?
Sources & Official References
Other rules in Cherokee County
Compare Cherokee County to another location·View the Georgia environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.