Monterey County, CA Environmental Rules: Flood Elevation Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Freeboard
1 foot above base flood elevation
Zone AO variant
1-2 feet above adjacent grade
Certification
Licensed surveyor or civil engineer
Administered by
HCD Floodplain Administrator
Flood vents
1 sq in per sq ft enclosed area

Summary

Monterey County Code Section 16.16.050(C) requires new construction and substantial improvements in Special Flood Hazard Areas to elevate the lowest floor, including any basement, at least one foot above the base flood elevation shown on the FIRM. The Housing and Community Development Department's Floodplain Administrator verifies compliance through elevation certification by a licensed surveyor or engineer.

City-specific rules exist: Salinas has its own flood elevation requirements rules that differ from Monterey County's county-level regulations. If you live in Salinas, check the city-specific page instead.

C.Elevation and Floodproofing.1.New construction and substantial improvement of any structure shall have the lowest floor, including basement, elevated to at least one (1) foot above the base flood elevation. Non-residential structures may meet the standards in Section 16.16.050.C.3. Upon completion of the structure the elevation of the lowest floor, including basement, shall be certified by a registered civil engineer or surveyor or verified by the County Building Inspector that elevation requirements have been met. Notification of compliance shall be recorded as set forth in Section 16.16.040.G.1.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 56).

Full Breakdown

16, Regulations for Floodplains, implements the county's National Flood Insurance Program obligations and applies wherever a Special Flood Hazard Area (SFHA) is mapped on the Flood Insurance Rate Map (FIRM), coastal and inland alike. 050(C)(1) requires that 'new construction and substantial improvement of any structure shall have the lowest floor, including basement, elevated to at least one (1) foot above the base flood elevation,' with compliance certified by a registered civil engineer or surveyor, or verified by the County Building Inspector, once the structure is complete.

050(C)(2) instead requires the lowest floor to sit at least one foot above the highest adjacent grade, or two feet if the FIRM shows no depth number. 050(C)(3), watertight to at least one foot above the base flood elevation and certified by a registered engineer or architect. 050(D) additionally requires enclosed areas below the lowest floor, such as parking or storage space, to include flood vents sized to at least one square inch of opening per square foot of enclosed area, so hydrostatic pressure cannot collapse the walls.

Attached garages built with the floor slab below the base flood elevation must be built of flood-resistant materials up to that same one-foot freeboard mark. 040 and can require a Letter of Map Revision based on Fill (LOMR-F) where a site has been filled above the base flood elevation.

Violations & Fines

The County, through the Floodplain Administrator, may take remedial action against Chapter 16.16 violations as specified in Section 16.16.030(C), and inspections under Section 16.16.040(M) can require correction before final approval. Because floodplain development also requires a building or floodplain development permit, uncertified or under-elevated construction can be held up at the lowest-floor inspection stage, before vertical construction continues, until a licensed surveyor or engineer confirms the one-foot freeboard has been met.

Frequently Asked Questions

How high above flood level must a new home be built in Monterey County?
Section 16.16.050(C)(1) requires the lowest floor of new construction or a substantial improvement in a Special Flood Hazard Area, including any basement, to sit at least one foot above the base flood elevation shown on the Flood Insurance Rate Map. A registered civil engineer or surveyor must certify the finished elevation, or the County Building Inspector must verify it.
Can a non-residential building in Monterey County use floodproofing instead of elevation?
Yes. Section 16.16.050(C)(3) lets non-residential structures be dry floodproofed to at least one foot above the base flood elevation instead of physically elevated, provided the walls are watertight, the structure can resist hydrostatic and hydrodynamic loads, and a registered engineer or architect certifies the design meets the standard.
What if my Monterey County lot is in Zone AO instead of a numbered flood zone?
Section 16.16.050(C)(2) applies a different freeboard in Zone AO: the lowest floor must sit at least one foot above the highest adjacent grade if the FIRM shows a depth number, or at least two feet above adjacent grade if no depth number is specified for the site.

Sources & Official References

Other rules in Monterey County

All Monterey County rules

California rules heatmap·Compare Monterey County to another location·View the California environmental rules overview

Get notified when Flood Elevation Requirements in Monterey County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Cities Across Monterey County