Salinas, CA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Freeboard required
- 2 feet above base flood elevation
- AO Zone rule
- 2 ft above mapped depth number
- Certification required
- Registered engineer or surveyor
- Certification timing
- Before and after foundation pour
- Nonresidential option
- Dry floodproof to same elevation
- Default BFE (Zone A)
- 2 ft above highest adjacent grade
Summary
New construction and substantial improvements in a Salinas special flood hazard area must have their lowest floor, including any basement, elevated at least two feet above the base flood elevation. In approximate Zone AO, elevation must clear the mapped depth number by two feet, or sit two feet above the highest adjacent grade if no depth number is shown. A licensed engineer or surveyor must certify the finished elevation.
(c)Elevation and Floodproofing.(1)Residential construction, new construction or substantial improvement of any structure shall have the lowest floor, including basement, elevated as follows:(A)In an AO Zone, elevated above the highest adjacent grade to a height exceeding the depth number specified in feet on the FIRM by two feet, or elevated at least two feet above the highest adjacent grade if no depth number is specified;(B)In an A Zone, elevated two feet (minimum) above the base flood elevation; such base flood elevation shall be determined by methods in Section 9-06.19(b) of this article.(C)In all other zones, elevated two feet (minimum) above the base flood elevation. Upon completion of the structure, the elevation of the lowest floor including basement shall be certified by a registered professional engineer or surveyor, and verified by the building official to be properly elevated. Such certification and verification shall be provided to the floodplain administrator both prior to pouring the foundation and immediately after such foundation pour.
Full Breakdown
Sec. 34(c) of the flood damage prevention article sets the city's freeboard standard, two feet above the minimum required by the National Flood Insurance Program. For residential construction it requires: in an AO Zone, elevation 'above the highest adjacent grade to a height exceeding the depth number specified in feet on the FIRM by two feet, or elevated at least two feet above the highest adjacent grade if no depth number is specified'; in an A Zone, elevation 'two feet (minimum) above the base flood elevation' using methods in Sec.
' Once the structure is finished, 'the elevation of the lowest floor including basement shall be certified by a registered professional engineer or surveyor, and verified by the building official to be properly elevated,' with that certification due to the Floodplain Administrator both before the foundation is poured and immediately after. Nonresidential buildings may instead be dry floodproofed to the same elevation, watertight, structurally able to resist hydrostatic and hydrodynamic loads, and certified by a registered engineer or architect (Sec. 34(c)(2)). Where the FIRM does not supply a base flood elevation, applicants in an approximate Zone A must have one established, either through an engineering study performed by a state-licensed civil engineer, agency data the Floodplain Administrator obtains, or a default of two feet above the highest adjacent grade absent evidence of deeper flooding, under Sec.
31. Manufactured homes carry the same two-foot freeboard under Sec. 48. The freeboard requirement traces back to the flood insurance study and map dated May 4, 1981 and November 4, 1981 respectively, adopted at Sec. 08.
Violations & Fines
A structure built below the required base flood elevation is presumed to be in violation under Sec. 9-06.52 until the elevation certificate or other required documentation is filed, and violating the flood damage prevention regulations is a misdemeanor under Sec. 9-06.09. Before the final inspection, the building official must receive certification of the required elevation prepared by a state-licensed land surveyor or civil engineer, per Sec. 9-06.51(d).
Frequently Asked Questions
How far above base flood elevation must a Salinas building sit?
Who has to certify the elevation of a new building in a Salinas flood zone?
Can a commercial building in Salinas skip the elevation requirement?
Sources & Official References
Other rules in Salinas
California rules heatmap·Compare Salinas to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.