Nicholasville, KY Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Residential lowest floor
- No lower than one (1.0) foot above base flood elevation
- AO zone, no depth number on FIRM
- At least two (2) feet above highest adjacent grade
- Enclosed-area openings
- Two openings, one square inch per square foot enclosed
- Elevation certification
- Registered professional engineer or surveyor, after completion
- Enforcing official
- Floodplain Administrator: the Mayor or designee (Sec. 9-21)
- Minimum fine on conviction
- No less than $100; each day a separate offense
Summary
In Nicholasville, new construction or substantial improvement of a residential structure in a special flood hazard area with base flood elevation data must have its lowest floor, including basement, crawlspace, mechanical equipment and ductwork, elevated no lower than one (1.0) foot above the base flood elevation. The Floodplain Administrator, the Mayor or designee, receives the elevation certification under Sec. 9-32.
In all special flood hazard areas where base flood elevation data have been provided, as set forth in Sec. 9-7, the following provisions are required: (1) Residential construction. New construction or substantial improvement of any residential structure (or manufactured home) shall have the lowest floor, including basement, crawlspace, mechanical equipment, and ductwork elevated no lower than one (1.0) foot above the base flood elevation. ... c. In all other zones, elevated one (1.0) foot above the base flood elevation. Upon the completion of the structure, the elevation of the lowest floor including basement shall be certified by a registered professional engineer or surveyor, and verified by the community building inspection department to be properly elevated. Such certification and verification shall be provided to the Floodplain Administrator.
Official source re-checked November 3, 2026: no newer edition of the code had been published (publisher’s edition: Local legislation current through Ord. No. 175-2024, dated 1-13-25 | State legislation current through 2024 Acts).
Full Breakdown
Sec. 9-32 sets the specific elevation standards for special flood hazard areas where base flood elevation data have been provided under Sec. 9-7. For residential construction the rule is one foot of freeboard: the lowest floor, together with the basement, crawlspace, mechanical equipment and ductwork, must be elevated no lower than one (1.0) foot above the base flood elevation. Where solid foundation perimeter walls raise the structure, openings sufficient for the unimpeded movement of floodwaters must be provided under division (3).
The zone rules differ. In an AO zone the structure is elevated above the highest adjacent grade to a height equal to or exceeding the depth number specified in feet on the FIRM, or at least two (2) feet above the highest adjacent grade if no depth number is specified. In an A zone where the Federal Emergency Management Agency has produced no technical data, the floor is elevated one (1.0) foot above the base flood elevation as determined by the community, and the Floodplain Administrator picks the method. In all other zones, a registered professional engineer or surveyor certifies the lowest floor elevation once the structure is complete, the community building inspection department verifies it, and both go to the Floodplain Administrator.
Non-residential buildings either meet the same elevation or are floodproofed below an elevation one (1.0) foot above the base flood elevation so the structure is watertight, with an engineer or architect certifying it. Fully enclosed areas below the lowest floor used only for parking, building access or storage need a minimum of two openings with a total net area of not less than one (1) square inch for every square foot of enclosed area, the bottom of each no higher than one (1) foot above grade. Manufactured homes in A, A1-30, AO, AH and AE zones must sit on a permanent foundation with the lowest floor at least one foot above the base flood elevation.
Violations & Fines
Development that does not follow Chapter 9, including development outside the terms of a floodplain construction permit, is a civil offense under Sec. 9-13(a). The Floodplain Administrator's office issues a notice of violation stating the remedy and a deadline, which can include a stop-work order. A citation follows if the remedy is not carried out, and the recipient has seven (7) days to correct the problem, pay the civil fine or request a hearing. On conviction under Sec. 9-13(d), the fine is no less than $100 or up to ten (10) days in jail, or both, plus costs, and each day is a separate offense.
Frequently Asked Questions
How high must a new house in a Nicholasville floodplain be elevated?
Who certifies the elevation after construction?
Can a store or warehouse be floodproofed instead of raised?
What is the penalty for building in the floodplain without following Chapter 9?
Sources & Official References
Other rules in Nicholasville
Compare Nicholasville to another location·View the Kentucky environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.