Key Facts

Freeboard
1 foot above base flood elevation (BFE)
Mechanical equipment
HVAC, ductwork must also clear BFE plus 1 ft
Flood vents
2 openings, 1 sq in per sq ft enclosed
Certification
As-built elevation cert. by licensed surveyor/engineer
Max penalty
$1,000 fine, 30 days jail, per day

Summary

Within Spalding County's S-1 flood hazard overlay, new construction and substantial improvements must sit at least one foot above the base flood elevation shown on FEMA's map, the county's freeboard cushion against underestimated flood heights. Heating, air conditioning and other service equipment must clear that same one-foot mark, and enclosures below an elevated lowest floor need flood vents sized to equalize water pressure automatically.

These county ordinances apply to unincorporated areas of Spalding County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

W.Freeboard: A factor of safety usually expressed in feet above a flood level for purposes of floodplain management. "Freeboard" tends to compensate for the many unknown factors that could contribute to flood heights greater than the height calculated for a selected size flood and floodway conditions, such as wave action, bridge openings, and the hydrological effect of urbanization of the watershed. ... 1.New construction and/or substantial improvements.a.Where base flood elevation data are available, new construction and/or substantial improvement of any structure or manufactured home shall have the lowest floor, including basement, elevated no lower than one (1) foot above the base flood elevation. Should solid foundation perimeter walls be used to elevate a structure, openings sufficient to facilitate equalization of flood hydrostatic forces on both sides of exterior walls shall be provided in accordance with standards of subsection 2005 A.4., "Elevated buildings." ... G.Penalties for violation. ... fined not more than one thousand dollars ($1,000.00) or imprisoned for not more than thirty (30) days, or both .

Full Breakdown

Section 2002 of the Spalding County Zoning Ordinance, Appendix IV, defines 'freeboard' as a factor of safety expressed in feet above a flood level that compensates for unknowns such as wave action and the hydrological effect of urbanizing a watershed. Section 2005(B)(1)(a) turns that concept into a hard number for the S-1 overlay: where base flood elevation data exist, new construction or a substantial improvement of any structure or manufactured home must have its lowest floor, including any basement, elevated no lower than one foot above the base flood elevation shown on the FEMA flood insurance rate map.

The same one-foot freeboard applies to mechanical systems under Section 2005(B)(1)(b), which requires heating and air conditioning equipment and components, including ductwork, to sit at or above that elevation. Builders who instead use solid foundation perimeter walls to raise a structure must add flood vents under Section 2005(A)(4): at least two openings totaling one square inch of net area for every square foot of enclosed space below the lowest floor, with the bottom of each opening no higher than one foot above grade, so hydrostatic pressure equalizes automatically during a flood.

That sub-floor enclosure can only be used for parking, limited storage, or entry to the elevated area, never finished living space. Non-residential buildings have a second path under Section 2005(B)(2): flood-proofing the structure watertight to one foot above the base flood elevation, certified by a registered professional engineer or architect. Compliance is verified twice, once at the application stage under Section 2004(B)(1) and again after construction under Section 2004(B)(2), when the permit holder must submit an as-built elevation certification prepared by a licensed surveyor or engineer before the zoning administrator signs off.

Violations & Fines

Building or substantially improving a structure below the required one-foot freeboard inside the S-1 overlay is a Section 2003 violation carrying a fine of up to one thousand dollars, up to thirty days in jail, or both, with each day of noncompliance a separate offense. Missing the as-built elevation certification required after construction under Section 2004 can also trigger a stop-work order until the deficiency is corrected.

Frequently Asked Questions

How much higher than the base flood elevation must a new house be built?
At least one foot. Section 2005(B)(1)(a) requires the lowest floor, including any basement, of new construction or a substantially improved structure to sit no lower than one foot above the base flood elevation shown on FEMA's flood insurance rate map for the parcel.
What if I build a crawlspace with solid foundation walls instead of piers?
You need flood vents. Section 2005(A)(4) requires at least two openings with a combined net area of one square inch per square foot of enclosed space below the lowest floor, positioned no higher than one foot above grade, so floodwater can enter and exit automatically and equalize pressure on the walls.
Can a business flood-proof instead of elevating?
Non-residential buildings can choose flood-proofing under Section 2005(B)(2): the structure and its utilities must be made watertight to one foot above the base flood elevation, with a registered professional engineer or architect certifying that the design meets that standard before the zoning administrator approves it.

Sources & Official References

Other rules in Spalding County

All Spalding County rules

Compare Spalding County to another location·View the Georgia environmental rules overview

Get notified when Flood Elevation Requirements in Spalding County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.